ORS 537.630: Time allowed for construction work under permit; extension; certificate of completion; survey; ground water right certificate; requirements for supplemental water right.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) As used in this section, “undeveloped portion” means the difference between the maximum rate or duty specified in a water right permit and the maximum rate or duty appropriated as of the later of: (a) June 29, 2005; (b) The time specified in the permit to perfect the water right; or (c) The time specified in the last-approved extension of time to perfect the water right. (2) Except for the holder of a permit for municipal, quasi-municipal, group domestic or group domestic expanded uses, the holder of a permit issued pursuant to ORS 537.625 shall prosecute the construction of a well or other means of developing and securing the ground water with reasonable diligence and complete the construction within a reasonable time fixed in the permit by the Water Resources Department, not to exceed seven years after the date of approval of the application. (3)(a) The holder of a right for quasi-municipal, group domestic or group domestic expanded uses shall complete construction of proposed works and apply water beneficially within seven years from the date on which a permit for such uses is issued under ORS 537.211. The construction must proceed with reasonable diligence and be completed within the time specified in the permit, not to exceed seven years. (b) Notwithstanding paragraph (a) of this subsection, the department may, for good cause shown, order and allow one extension of time to complete construction and apply water beneficially, not exceeding: (A) Twenty years from the date that the extension is approved for quasi-municipal use. (B) Ten years from the date the extension is approved for group domestic use or group domestic expanded use. (c) In determining the extension under paragraph (b) of this subsection, the department shall give due weight to considerations in ORS 539.010 (5) and to whether other governmental requirements relating to the project have significantly delayed completion of the construction and beneficial application of the right. (4) The holder of a permit for municipal use shall commence and complete the construction of any proposed works within 20 years from the date on which the permit for municipal use is issued under ORS 537.625. The construction must proceed with reasonable diligence and be completed within the time specified in the permit, not to exceed 20 years. However, the department may order and allow an extension of time to complete construction or to perfect a water right beyond the time specified in the permit under the following conditions: (a) The holder shows good cause. In determining the extension, the department shall give due weight to the considerations described under ORS 539.010 (5) and to whether other governmental requirements relating to the project have significantly delayed completion of construction or perfection of the right; (b) The extension of time is conditioned to require that the holder submit and obtain department approval of a water management and conservation plan; (c) The extension of time is conditioned to provide that the holder may appropriate the undeveloped portion of the permit only upon approval by the department of a water management and conservation plan; and (d) For the first extension issued after June 29, 2005, for a permit for municipal use issued before November 2, 1998, the department finds that the undeveloped portion of the permit is conditioned to maintain, in the portions of waterways affected by water use under the permit, the persistence of fish species listed as sensitive, threatened or endangered under state or federal law. The department shall base its finding on existing data and upon the advice of the State Department of Fish and Wildlife. An existing fish protection agreement between the permit holder and a state or federal agency that includes conditions to maintain the persistence of any listed fish species in the affected portion of the waterway is conclusive for purposes of the finding. (5) If the construction of any well or other means of developing and securing the ground water is completed after the date of approval of the application for a permit under ORS 537.625, within 30 days after the completion, or if the construction is completed before the date of approval, within 30 days after the date of approval, the permit holder shall file a certificate of completion with the Water Resources Department, disclosing: (a) The depth to the water table; (b) The depth, diameter and type of each well, and the kind and amount of the casing; (c) The capacity of the well pump in gallons per minute and the drawdown thereof; (d) The identity of the record owner of any property that was described in the application for a permit under ORS 537.625 but is not included in the certificate of completion; and (e) Any other information the department considers necessary. (6) Upon completion of beneficial use necessary to secure the ground water as required under this section, the permit holder shall hire a water right examiner certified under ORS 537.798 to survey the appropriation. Within one year after applying the water to beneficial use or the beneficial use date allowed in the permit, the permit holder shall submit the survey as required by the Water Resources Department to the department along with the certificate of completion required under subsection (5) of this section. If any property described in the permit is not included in the request for a water right certificate, the holder of the permit shall state the identity of the record owner of that property. (7) After the department has received a certificate of completion and a copy of the survey as required by subsections (5) and (6) of this section that show, to the satisfaction of the department, that an appropriation has been perfected in accordance with the provisions of ORS 537.505 to 537.795 and 537.992, except as provided in subsection (8) of this section, the department shall issue a ground water right certificate of the same character as that described in ORS 537.700. The certificate shall be recorded and transmitted to the applicant as provided in ORS 537.700. (8) The department may not issue a water right certificate for municipal use under this section if: (a) An extension of time is required; and (b) The order approving the extension of time has not become final by operation of law or on appeal. (9) The procedure for cancellation of a permit shall be as provided in ORS 537.260. (10) Notwithstanding ORS 537.410, for purposes of obtaining a water right certificate under subsection (7) of this section for a supplemental water right, the holder of a permit shall have a facility capable of handling the full rate and duty of water requested from the supplemental source and be otherwise ready, willing and able to use the amount of water requested, up to the amount of water approved in the water right permit. To obtain a certificate for a supplemental water right, the holder is not required to have actually used water from the supplemental source if: (a) Water was available from the source of the primary water right and the primary water right was used pursuant to the terms of the primary water right; or (b) The nonuse of water from the supplemental source occurred during a period of time within which the exercise of the supplemental water right permit was not necessary due to climatic conditions. [1955 c.708 §12; 1959 c.437 §5; 1985 c.617 §2; 1985 c.673 §202; 1987 c.542 §8; 1995 c.367 §3; 1995 c.416 §34; 1997 c.446 §8; 1999 c.453 §2; 2005 c.410 §2; 2017 c.704 §4; 2025 c.282 §26] 537.630. (1) As used in this section, “undeveloped portion” means the difference between the maximum rate or duty specified in a water right permit and the maximum rate or duty appropriated as of the later of: (a) June 29, 2005; (b) The time specified in the permit to perfect the water right; or (c) The time specified in the last-approved extension of time to perfect the water right. (2) Except for the holder of a permit for municipal use, the holder of a permit issued pursuant to ORS 537.625 shall prosecute the construction of a well or other means of developing and securing the ground water with reasonable diligence and complete the construction within a reasonable time fixed in the permit by the Water Resources Department, not to exceed five years after the date of approval of the application. However, the department, for good cause shown, shall order and allow an extension of time, including an extension beyond the five-year period, for the completion of the well or other means of developing and securing the ground water or for complete application of water to beneficial use. In determining the extension, the department shall give due weight to the considerations described under ORS 539.010 (5) and to whether other governmental requirements relating to the project have significantly delayed completion of construction or perfection of the right. (3) The holder of a permit for municipal use shall commence and complete the construction of any proposed works within 20 years from the date on which the permit for municipal use is issued under ORS 537.625. The construction must proceed with reasonable diligence and be completed within the time specified in the permit, not to exceed 20 years. However, the department may order and allow an extension of time to complete construction or to perfect a water right beyond the time specified in the permit under the following conditions: (a) The holder shows good cause. In determining the extension, the department shall give due weight to the considerations described under ORS 539.010 (5) and to whether other governmental requirements relating to the project have significantly delayed completion of construction or perfection of the right; (b) The extension of time is conditioned to require that the holder submit and obtain department approval of a water management and conservation plan; (c) The extension of time is conditioned to provide that the holder may appropriate the undeveloped portion of the permit only upon approval by the department of a water management and conservation plan; and (d) For the first extension issued after June 29, 2005, for a permit for municipal use issued before November 2, 1998, the department finds that the undeveloped portion of the permit is conditioned to maintain, in the portions of waterways affected by water use under the permit, the persistence of fish species listed as sensitive, threatened or endangered under state or federal law. The department shall base its finding on existing data and upon the advice of the State Department of Fish and Wildlife. An existing fish protection agreement between the permit holder and a state or federal agency that includes conditions to maintain the persistence of any listed fish species in the affected portion of the waterway is conclusive for purposes of the finding. (4) If the construction of any well or other means of developing and securing the ground water is completed after the date of approval of the application for a permit under ORS 537.625, within 30 days after the completion, or if the construction is completed before the date of approval, within 30 days after the date of approval, the permit holder shall file a certificate of completion with the Water Resources Department, disclosing: (a) The depth to the water table; (b) The depth, diameter and type of each well, and the kind and amount of the casing; (c) The capacity of the well pump in gallons per minute and the drawdown thereof; (d) The identity of the record owner of any property that was described in the application for a permit under ORS 537.625 but is not included in the certificate of completion; and (e) Any other information the department considers necessary. (5) Upon completion of beneficial use necessary to secure the ground water as required under this section, the permit holder shall hire a water right examiner certified under ORS 537.798 to survey the appropriation. Within one year after applying the water to beneficial use or the beneficial use date allowed in the permit, the permit holder shall submit the survey as required by the Water Resources Department to the department along with the certificate of completion required under subsection (4) of this section. If any property described in the permit is not included in the request for a water right certificate, the holder of the permit shall state the identity of the record owner of that property. (6) After the department has received a certificate of completion and a copy of the survey as required by subsections (4) and (5) of this section that show, to the satisfaction of the department, that an appropriation has been perfected in accordance with the provisions of ORS 537.505 to 537.795 and 537.992, except as provided in subsection (7) of this section, the department shall issue a ground water right certificate of the same character as that described in ORS 537.700. The certificate shall be recorded and transmitted to the applicant as provided in ORS 537.700. (7) The department may not issue a water right certificate for municipal use under this section if: (a) An extension of time is required; and (b) The order approving the extension of time has not become final by operation of law or on appeal. (8) The procedure for cancellation of a permit shall be as provided in ORS 537.260. (9) Notwithstanding ORS 537.410, for purposes of obtaining a water right certificate under subsection (6) of this section for a supplemental water right, the holder of a permit shall have a facility capable of handling the full rate and duty of water requested from the supplemental source and be otherwise ready, willing and able to use the amount of water requested, up to the amount of water approved in the water right permit. To obtain a certificate for a supplemental water right, the holder is not required to have actually used water from the supplemental source if: (a) Water was available from the source of the primary water right and the primary water right was used pursuant to the terms of the primary water right; or (b) The nonuse of water from the supplemental source occurred during a period of time within which the exercise of the supplemental water right permit was not necessary due to climatic conditions.
Official history and status
History: Note: The amendments to 537.630 by section 26, chapter 282, Oregon Laws 2025, become operative April 1, 2026. See section 48, chapter 282, Oregon Laws 2025, as amended by section 21c, chapter 575, Oregon Laws 2025. The text that is operative until April 1, 2026, is set forth for the user’s convenience. Note: See second note under 537.230.
Administrative rules citing this section
- OAR 690-013-0005: Introduction — implements
- OAR 690-013-0010: Definitions — implements
- OAR 690-013-0030: Eligibility to Petition — implements
- OAR 690-013-0050: Individual Applications — implements
- OAR 690-013-0070: Interim Transfers — implements
- OAR 690-013-0100: District Petitions — implements
- OAR 690-013-0110: Requests for Additional Information — implements
- OAR 690-013-0150: District Shall Certify Petition — implements
- OAR 690-013-0310: Processing of Petition — implements
- OAR 690-013-0350: Field Verification of the Petition and Map — implements
- OAR 690-014-0100: Minimum Requirements for Claims of Beneficial Use for Permits and Transfer Final Orders — implements
- OAR 690-014-0110: Claim of Beneficial Use: General Standards — implements
- OAR 690-014-0170: Minimum Requirements for Maps for Permit or Transfer Final Order Claims of Beneficial Use — implements
- OAR 690-014-0190: Time Limit for Filing Claim of Beneficial Use — implements
- OAR 690-190-0005: Purpose and Applicability — implements
- OAR 690-190-0010: Definitions — implements
- OAR 690-190-0010: Definitions — authority
- OAR 690-190-0100: Recording Requirements — implements
- OAR 690-190-0100: Recording Requirements — authority
- OAR 690-190-0200: Compliance and Enforcement — implements
- OAR 690-190-0200: Compliance and Enforcement — authority
- OAR 690-200-0005: Basis for Regulatory Authority — implements
- OAR 690-200-0005: Basis for Regulatory Authority — authority
- OAR 690-200-0020: General Statement About the Standards — implements
- OAR 690-200-0020: General Statement About the Standards — authority
- OAR 690-200-0021: Special Standards — implements
- OAR 690-200-0021: Special Standards — authority
- OAR 690-200-0027: Restrictions on Water Supply Well Construction and Use in Critical Groundwater Areas or Areas Withdrawn by Commission Order — implements
- OAR 690-200-0027: Restrictions on Water Supply Well Construction and Use in Critical Groundwater Areas or Areas Withdrawn by Commission Order — authority
- OAR 690-200-0028: Designated Special Area Standards — implements
- OAR 690-200-0028: Designated Special Area Standards — authority
- OAR 690-200-0046: Perched Ground Water — implements
- OAR 690-200-0046: Perched Ground Water — authority
- OAR 690-200-0050: Definitions — implements
- OAR 690-200-0050: Definitions — authority
- OAR 690-205-0005: License or Permit Required to Construct Water Supply Wells — implements
- OAR 690-205-0005: License or Permit Required to Construct Water Supply Wells — authority
- OAR 690-205-0010: Water Supply Well Constructor License Examination — implements
- OAR 690-205-0010: Water Supply Well Constructor License Examination — authority
- OAR 690-205-0020: Water Supply Well Constructor’s License, Experience Requirements, Trainee Card and Temporary Authorization — implements
- OAR 690-205-0020: Water Supply Well Constructor’s License, Experience Requirements, Trainee Card and Temporary Authorization — authority
- OAR 690-205-0025: Term of Water Well Constructor License and License Fees — implements
- OAR 690-205-0025: Term of Water Well Constructor License and License Fees — authority
- OAR 690-205-0045: Continuing Education Requirement — implements
- OAR 690-205-0045: Continuing Education Requirement — authority
- OAR 690-205-0175: Landowner Well Construction Permit, Fee and Bond — implements
- OAR 690-205-0175: Landowner Well Construction Permit, Fee and Bond — authority
- OAR 690-205-0200: Water Supply Well Construction Notice Required (Start Card) — implements
- OAR 690-205-0200: Water Supply Well Construction Notice Required (Start Card) — authority
- OAR 690-205-0205: Start Card Reporting Requirements — implements
- OAR 690-205-0205: Start Card Reporting Requirements — authority
- OAR 690-205-0210: Well Report Required (Water Supply Well Log) — implements
- OAR 690-205-0210: Well Report Required (Water Supply Well Log) — authority
- OAR 690-210-0130: Sealing of Wells in Unconsolidated Formations Without Significant Clay Beds — implements
- OAR 690-210-0130: Sealing of Wells in Unconsolidated Formations Without Significant Clay Beds — authority
- OAR 690-210-0140: Sealing of Water Supply Wells in Unconsolidated Formations with Significant Clay Beds — implements
- OAR 690-210-0140: Sealing of Water Supply Wells in Unconsolidated Formations with Significant Clay Beds — authority
- OAR 690-210-0150: Sealing of Water Supply Wells in Consolidated Formations — implements
- OAR 690-210-0150: Sealing of Water Supply Wells in Consolidated Formations — authority
- OAR 690-210-0155: Additional Standards for Artesian Water Supply Wells — implements
- OAR 690-210-0155: Additional Standards for Artesian Water Supply Wells — authority
- OAR 690-210-0160: Additional Standards for Filter Pack Wells with Surface Casing — implements
- OAR 690-210-0160: Additional Standards for Filter Pack Wells with Surface Casing — authority
- OAR 690-210-0170: Additional Standards for Filter Pack Wells without Surface Casing — implements
- OAR 690-210-0170: Additional Standards for Filter Pack Wells without Surface Casing — authority
- OAR 690-210-0180: Additional Standards for Driven or Jetted Wells — implements
- OAR 690-210-0180: Additional Standards for Driven or Jetted Wells — authority
- OAR 690-210-0190: Steel Casing — implements
- OAR 690-210-0190: Steel Casing — authority
- OAR 690-210-0220: Plastic Casing Joints — implements
- OAR 690-210-0220: Plastic Casing Joints — authority
- OAR 690-210-0230: Inner Casing — implements
- OAR 690-210-0230: Inner Casing — authority
- OAR 690-210-0240: Casing Shall be Centered — implements
- OAR 690-210-0240: Casing Shall be Centered — authority
- OAR 690-210-0270: Pitless Well Adapters and Units — implements
- OAR 690-210-0270: Pitless Well Adapters and Units — authority
- OAR 690-210-0280: Access Ports, Dedicated Measuring Tubes and Airlines — implements
- OAR 690-210-0280: Access Ports, Dedicated Measuring Tubes and Airlines — authority
- OAR 690-210-0290: Liner Pipe — implements
- OAR 690-210-0290: Liner Pipe — authority
- OAR 690-210-0320: Methods of Placement of Cement Grout or Concrete — implements
- OAR 690-210-0320: Methods of Placement of Cement Grout or Concrete — authority
- OAR 690-210-0380: Disinfection of a Well — implements
- OAR 690-210-0380: Disinfection of a Well — authority
- OAR 690-210-0400: Construction of Dug Wells — implements
- OAR 690-210-0400: Construction of Dug Wells — authority
- OAR 690-210-0410: Buried Slab Construction — implements
- OAR 690-210-0410: Buried Slab Construction — authority
- OAR 690-210-0420: Surface Curbing — implements
- OAR 690-210-0420: Surface Curbing — authority
- OAR 690-215-0005: Prevention of Groundwater Contamination, Health Hazard, and Waste — implements
- OAR 690-215-0005: Prevention of Groundwater Contamination, Health Hazard, and Waste — authority
- OAR 690-215-0017: Down Well Continuous Water Treatment and Back-Siphon Prevention Devices — implements
- OAR 690-215-0017: Down Well Continuous Water Treatment and Back-Siphon Prevention Devices — authority
- OAR 690-215-0055: Well Identification Label Maintenance — implements
- OAR 690-215-0055: Well Identification Label Maintenance — authority
- OAR 690-215-0060: Access Ports, Dedicated Measuring Tubes and Airlines — implements
- OAR 690-215-0060: Access Ports, Dedicated Measuring Tubes and Airlines — authority
- OAR 690-215-0070: Pressure Gauge — implements
- OAR 690-215-0070: Pressure Gauge — authority
- OAR 690-215-0201: Dedicated Measuring Tube — implements
- OAR 690-215-0201: Dedicated Measuring Tube — authority
- OAR 690-220-0050: Abandonment of Uncased Wells — implements
- OAR 690-220-0050: Abandonment of Uncased Wells — authority
- OAR 690-225-0020: Investigation of Alleged Violations — implements
- OAR 690-225-0020: Investigation of Alleged Violations — authority
- OAR 690-225-0030: Enforcement Actions — implements
- OAR 690-225-0030: Enforcement Actions — authority
- OAR 690-225-0110: Schedule of Civil Penalties — implements
- OAR 690-225-0110: Schedule of Civil Penalties — authority
- OAR 690-240-0005: Introduction — implements
- OAR 690-240-0005: Introduction — authority
- OAR 690-240-0006: Special Standards — implements
- OAR 690-240-0006: Special Standards — authority
- OAR 690-240-0010: Definitions — implements
- OAR 690-240-0010: Definitions — authority
- OAR 690-240-0024: Well Identification Label — implements
- OAR 690-240-0024: Well Identification Label — authority
- OAR 690-240-0026: Well Identification Label Maintenance — implements
- OAR 690-240-0026: Well Identification Label Maintenance — authority
- OAR 690-240-0060: Monitoring Well Constructor License Examination — implements
- OAR 690-240-0060: Monitoring Well Constructor License Examination — authority
- OAR 690-240-0065: Monitoring Well Constructor License, Experience Requirements, Trainee Card and Temporary Authorization — implements
- OAR 690-240-0065: Monitoring Well Constructor License, Experience Requirements, Trainee Card and Temporary Authorization — authority
- OAR 690-240-0070: Terms of Monitoring Well Constructor License and License Fees — implements
- OAR 690-240-0070: Terms of Monitoring Well Constructor License and License Fees — authority
- OAR 690-240-0210: Continuing Education Requirement — implements
- OAR 690-240-0210: Continuing Education Requirement — authority
- OAR 690-240-0340: Landowner Well Construction Permit, Fee and Bond — authority
- OAR 690-240-0375: Monitoring Well Construction Notice Required (Start Card) — implements
- OAR 690-240-0375: Monitoring Well Construction Notice Required (Start Card) — authority
- OAR 690-240-0385: Start Card Reporting Requirements — implements
- OAR 690-240-0385: Start Card Reporting Requirements — authority
- OAR 690-240-0395: Monitoring Well Report Required (Monitoring Well Log) — implements
- OAR 690-240-0395: Monitoring Well Report Required (Monitoring Well Log) — authority
- OAR 690-240-0410: Monitoring Well Construction: General — implements
- OAR 690-240-0410: Monitoring Well Construction: General — authority
- OAR 690-240-0560: Investigation of Alleged Violations — implements
- OAR 690-240-0560: Investigation of Alleged Violations — authority
- OAR 690-240-0580: Enforcement Actions — implements
- OAR 690-240-0580: Enforcement Actions — authority
- OAR 690-240-0640: Schedule of Civil Penalties — implements
- OAR 690-240-0640: Schedule of Civil Penalties — authority
- OAR 690-260-0030: Notice of Violation — implements
- OAR 690-260-0030: Notice of Violation — authority
- OAR 690-260-0040: Classification of Violations — implements
- OAR 690-260-0040: Classification of Violations — authority
- OAR 690-260-0060: Notice of Assessment of Civil Penalty — implements
- OAR 690-260-0060: Notice of Assessment of Civil Penalty — authority
- OAR 690-300-0010: Definitions — authority
- OAR 690-315-0010: Purpose and Definitions — implements
- OAR 690-315-0020: Application for Extension of Time for Other Than Municipal and Quasi-Municipal Water Use Permits — implements
- OAR 690-315-0030: Application for Extension of Time to Begin Construction on Storage Projects — implements
- OAR 690-315-0040: Criteria for Department Review of Extension Applications for Other Than Municipal and Quasi-Municipal Water Use Permits — implements
- OAR 690-315-0050: Department Action on Extension Applications — implements
- OAR 690-315-0060: Proposed Final Order Hearing Rights — implements
- OAR 690-315-0070: Application for Extension of Time for Municipal and Quasi-Municipal Water Use Permits — implements
- OAR 690-315-0080: Criteria for Department Review of Extension Applications for Municipal and Quasi-Municipal Water Use Permits — implements
- OAR 690-315-0090: Time of Extensions and Additional Development of Municipal and Quasi-Municipal Water Use Permits — implements
- OAR 690-315-0100: Department Action on Extension Applications by Holders of Municipal Water Supply Permits — implements
- OAR 690-410-0070: Water Allocation — authority
This rule cites
- ORS 537.625 — resolved
- ORS 537.211 — resolved
- ORS 539.010 — resolved
- ORS 537.798 — resolved
- ORS 537.505 — resolved
- 537.795 — resolved
- 537.992 — resolved
- ORS 537.700 — resolved
- ORS 537.260 — resolved
- ORS 537.410 — resolved
Cited by
- ORS 536.050: Fees; rules; refunds; waiver and reduction of certain fees.
- ORS 537.040: Registration of water for road construction, maintenance or reconstruction; fee; annual renewal statement; limitations; rules.
- ORS 537.141: Uses of water not requiring water right application, permit or certificate; rules.
- ORS 537.143: Limited license to use or store surface or ground water or to use stored water; rules.
- ORS 537.230: Time allowed for construction of irrigation or other work; extension; survey; map; requirements for supplemental water right.
- ORS 537.385: Extension of irrigation season; rules; limitations.
- ORS 537.545: Exempt uses; map; filing of use; fee; rules.
- ORS 537.797: Criteria for certification to determine work completion; rules.
- OAR 690-315-0010: Purpose and Definitions
- OAR 690-315-0020: Application for Extension of Time for Other Than Municipal and Quasi-Municipal Water Use Permits
- OAR 690-315-0040: Criteria for Department Review of Extension Applications for Other Than Municipal and Quasi-Municipal Water Use Permits
- OAR 690-315-0070: Application for Extension of Time for Municipal and Quasi-Municipal Water Use Permits
- OAR 690-315-0080: Criteria for Department Review of Extension Applications for Municipal and Quasi-Municipal Water Use Permits
- OAR 690-320-0010: Extension of Time Limits
- OAR 690-330-0010: Proof of Appropriation
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors537.html