OAR 690-210-0320: Methods of Placement of Cement Grout or Concrete
Edition: Current OARD snapshotEffective: 2023-07-01Last verified: 2026-09-07
Cement grout or concrete used as a sealing material in a well shall be placed or forced upward from the bottom to completely fill the annular space to be grouted and shall be placed in one continuous operation without significant interruption. If temporary outer surface casing is used in the construction of the well, it shall be withdrawn as the grout or concrete is placed. (For acceptable methods of placement, see Appendix 210-3 and Figure 210-1). [ED. NOTE: To view attachments referenced in rule text, click here to view rule.]
Official history and status
Statutory/Other Authority: ORS 536.090, ORS 537.505-537.795, ORS 536.027, ORS 536.900 & ORS 537.992
Statutes/Other Implemented: ORS 536.090, ORS 537.505-537.795, ORS 536.900 & ORS 537.992
History: WRD 5-2023, amend filed 06/22/2023, effective 07/01/2023 WRD 1-2017, f. & cert. ef. 2-16-17 WRD 5-2016, f. & cert. ef. 9-6-16 WRD 5-2015, f. & cert. ef. 7-1-15 WRD 7-2001, f. & cert. ef. 11-15-01 WRD 7-1988, f. & cert. ef. 6-29-88 WRD 13-1986, f. 10-7-86, cert. ef. 11-1-86, Renumbered from 690-061-0021 & 690-061-0096 WRD 9-1978, f. 12-12-78, cert. ef. 1-1-79
This rule cites
No citations extracted.
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/