(1) Notwithstanding ORS 517.810 and 517.830, the State Department of Geology and Mineral Industries may issue a temporary operating permit to a person if: (a) After consultation, the local jurisdiction with land use authority over the permitted site does not raise substantive objections to the issuance of the permit; (b) All cooperating agencies approve of the permit issuance; and (c) There is no objection from persons owning property adjacent to the permitted site. (2) A temporary operating permit issued under this section is subject to reasonable limitations that may be prescribed by the department. (3) Within 30 days after issuing the temporary operating permit, the operator shall: (a) Comply with the bond and security requirements established by ORS 517.810; (b) Pay any applicable fee pursuant to ORS 517.800; and (c) Submit a reclamation plan to the department. (4) The governing board of the department shall adopt rules governing the issuance of temporary operating permits. The rules shall include provisions: (a) Ensuring opportunities for notice and comment by federal agencies; (b) Specifying the terms of a temporary operating permit; and (c) Establishing procedures for converting a temporary operating permit to a standard operating permit. [2005 c.34 §4; 2017 c.736 §14]
Administrative rules citing this section
- OAR 632-030-0026: On-Site Construction Waiver — implements
- OAR 632-030-0041: Permit and Exemption Transfer — implements
- OAR 632-030-0049: Emergency Operating Permits — implements
- OAR 632-030-0052: Temporary Operating Permits — implements
- OAR 632-037-0005: Purpose — implements
- OAR 632-037-0005: Purpose — authority
- OAR 632-037-0010: Definitions — authority
- OAR 632-037-0015: State and Federal Agency Coordination — authority
- OAR 632-037-0020: Project Coordinating Committee — authority
- OAR 632-037-0025: Technical Review Team — authority
- OAR 632-037-0030: Public Notice Procedure — authority
- OAR 632-037-0035: Notice of Intent — authority
- OAR 632-037-0040: Notice of Prospective Applicant’s Readiness to Collect Baseline Data — authority
- OAR 632-037-0045: Content — authority
- OAR 632-037-0050: General Information — authority
- OAR 632-037-0055: Existing Environment — Baseline Data — authority
- OAR 632-037-0060: Operating Plan — authority
- OAR 632-037-0070: Reclamation and Closure Plan — authority
- OAR 632-037-0075: Alternatives Analysis — authority
- OAR 632-037-0077: Additional Requirements — authority
- OAR 632-037-0080: Notice to Proceed — authority
- OAR 632-037-0085: Environmental Evaluation — authority
- OAR 632-037-0090: Socioeconomic Impact Analysis — authority
- OAR 632-037-0095: Permitting Agency Action on a Consolidated Application — authority
- OAR 632-037-0100: Cooperating Agency Action on a Consolidated Application — authority
- OAR 632-037-0105: Consolidated Public Hearing; Final Permits — authority
- OAR 632-037-0110: Appeals; Consolidated Contested Case Hearing — authority
- OAR 632-037-0115: Judicial Review — authority
- OAR 632-037-0118: Best Available Practicable and Necessary Technology — authority
- OAR 632-037-0120: Mine Operation Standards — authority
- OAR 632-037-0125: Fish and Wildlife Standards — authority
- OAR 632-037-0130: Reclamation and Mine Closure Standards — authority
- OAR 632-037-0135: Financial Security — authority
- OAR 632-037-0140: Obtaining Financial Security Release — authority
- OAR 632-037-0145: Permit Modifications — authority
- OAR 632-037-0150: Civil Penalties — authority
- OAR 632-037-0155: Fees — authority
This rule cites
- ORS 517.810 — resolved
- 517.830 — resolved
- ORS 517.800 — resolved
Cited by