ORS 517.830: Operating permit approval process; appeal from denial of plan; consolidated application process.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) Upon receipt of an application for an operating permit, the State Department of Geology and Mineral Industries shall: (a) Inspect the operating site described in the application; (b) Provide notice to the local jurisdiction and an opportunity for the local jurisdiction to, within 30 days after the date of the notice, request that the department delay a decision on an operating permit and reclamation plan as provided in subsection (4) of this section; and (c) If the application is not subject to the consolidated application process under ORS 517.952 to 517.989, provide notice to each federal and state permitting agency, as defined in ORS 517.952, and each cooperating agency and provide an opportunity for the agencies to, within 30 days after the date of the notice, respond in writing to the department identifying reasonably expected adverse effects of the proposed mining operation on land, air, water or wildlife resources. (2) Within 90 days after the date that the application and the required permit fee are received, the department shall issue the operating permit applied for or, if it considers the application incomplete, return the application to the applicant for correction of the deficiencies indicated by the department. An operating permit that is not subject to ORS 517.952 to 517.989 shall contain reasonable conditions designed to avoid or minimize an adverse effect identified by an agency pursuant to subsection (1)(c) of this section, provided: (a) A permit issued by a federal, state or local permitting agency approving the mining operation does not include provisions to mitigate the adverse effect; and (b) The land use decision issued by the local government approving the mining operation does not include provisions to mitigate the adverse effect. (3) Failure by the department to act upon the reclamation plan submitted with an application for an operating permit within the 90-day period referred to in subsection (2) of this section is not a denial by the department of the operating permit applied for. The department, pending final approval of a reclamation plan, may issue a provisional permit subject to reasonable limitations that may be prescribed by the department and conditioned upon the applicant’s compliance with the bond and security requirements established by ORS 517.810. (4)(a) Notwithstanding subsections (2) and (3) of this section, if an application involves an aggregate site that requires a permit issued pursuant to ORS 215.427 or 227.178, and if the local jurisdiction requests that the application not be decided until the local jurisdiction has taken final action, the department shall make a final decision on the operating permit and reclamation plan no later than 165 days after the date a complete land use application is submitted to the local jurisdiction, unless the applicant agrees to allow additional time under ORS 215.427, 215.429, 227.178 or 227.179. If a plan amendment is required as part of issuance of a permit, the provisions of paragraph (b) of this subsection apply. The department may not approve an operating permit and reclamation plan if the land use application is denied. (b) Notwithstanding subsections (2) and (3) of this section, if an application involves an aggregate site that requires amendment to a comprehensive plan, as defined in ORS 197.015, and if the local jurisdiction requests that the application not be decided until the local jurisdiction has taken final action on the plan amendment, the department may not make a final decision on the operating permit and reclamation plan until the local jurisdiction has taken final action on the plan amendment. The department shall make its final decision within 45 days of the date that the local jurisdiction has taken final action on the plan amendment. The department may not approve an operating permit and reclamation plan if the plan amendment is denied. (5) Conditions and requirements imposed on an operating permit and reclamation plan, and modifications thereto, issued subsequent to issuance of a local jurisdiction permit shall be compatible with the requirements and conditions of the local government permit, unless more stringent requirements are necessary to comply with the provisions of ORS 517.750 to 517.901. (6)(a) If a local jurisdiction does not request that the department delay a decision on an operating permit and reclamation plan as provided in subsections (1)(b) and (4) of this section, the department shall, prior to issuing the operating permit, give the local jurisdiction notice and an opportunity to provide comments and the following information about the proposed operating permit and reclamation plan: (A) Information about any applicable local land use regulations; (B) Whether the site described in the proposed operating permit and reclamation plan is included on a local government inventory required by any open spaces, scenic and historic areas and natural resources land use planning goal; (C) A statement that an application has or has not been filed for local approval; and (D) Any other information that the local jurisdiction considers pertinent in its review of the application. (b) A local jurisdiction shall respond to a notice provided under paragraph (a) of this subsection within 35 days after the date of the notice. (7) If the department refuses to approve a submitted reclamation plan, it shall notify the applicant, in writing, of its reasons for the refusal to approve the reclamation plan, including additional requirements as may be prescribed by the department for inclusion in the reclamation plan. Within 60 days after the receipt of the notice, the applicant shall comply with the additional requirements prescribed by the department for the reclamation plan or file with the department a notice of appeal from the decision of the department with respect to the reclamation plan. If a notice of appeal is filed with the department by the applicant, the department may issue a provisional permit to the applicant. (8) If an application is submitted as part of the consolidated application process under ORS 517.952 to 517.989, review of the application and approval or denial of the application shall be in accordance with ORS 517.952 to 517.989. However, the review and approval or denial shall take into consideration all policy considerations for issuing a permit under ORS 517.702 to 517.989. [1971 c.719 §6; 1975 c.724 §5; 1985 c.292 §10; 1991 c.243 §2; 1991 c.735 §29; 1999 c.353 §5; 1999 c.492 §4; 1999 c.533 §13; 2001 c.104 §226; 2007 c.318 §8; 2015 c.492 §1; 2017 c.736 §5]
Administrative rules citing this section
- OAR 632-030-0024: Inspections — implements
- OAR 632-030-0026: On-Site Construction Waiver — implements
- OAR 632-030-0041: Permit and Exemption Transfer — implements
- OAR 632-030-0049: Emergency Operating Permits — implements
- OAR 632-030-0052: Temporary Operating Permits — implements
- OAR 632-037-0005: Purpose — implements
- OAR 632-037-0005: Purpose — authority
- OAR 632-037-0010: Definitions — authority
- OAR 632-037-0015: State and Federal Agency Coordination — authority
- OAR 632-037-0020: Project Coordinating Committee — authority
- OAR 632-037-0025: Technical Review Team — authority
- OAR 632-037-0030: Public Notice Procedure — authority
- OAR 632-037-0035: Notice of Intent — authority
- OAR 632-037-0040: Notice of Prospective Applicant’s Readiness to Collect Baseline Data — authority
- OAR 632-037-0045: Content — authority
- OAR 632-037-0050: General Information — authority
- OAR 632-037-0055: Existing Environment — Baseline Data — authority
- OAR 632-037-0060: Operating Plan — authority
- OAR 632-037-0070: Reclamation and Closure Plan — authority
- OAR 632-037-0075: Alternatives Analysis — authority
- OAR 632-037-0077: Additional Requirements — authority
- OAR 632-037-0080: Notice to Proceed — authority
- OAR 632-037-0085: Environmental Evaluation — authority
- OAR 632-037-0090: Socioeconomic Impact Analysis — authority
- OAR 632-037-0095: Permitting Agency Action on a Consolidated Application — authority
- OAR 632-037-0100: Cooperating Agency Action on a Consolidated Application — authority
- OAR 632-037-0105: Consolidated Public Hearing; Final Permits — authority
- OAR 632-037-0110: Appeals; Consolidated Contested Case Hearing — authority
- OAR 632-037-0115: Judicial Review — authority
- OAR 632-037-0118: Best Available Practicable and Necessary Technology — authority
- OAR 632-037-0120: Mine Operation Standards — authority
- OAR 632-037-0125: Fish and Wildlife Standards — authority
- OAR 632-037-0130: Reclamation and Mine Closure Standards — authority
- OAR 632-037-0135: Financial Security — authority
- OAR 632-037-0140: Obtaining Financial Security Release — authority
- OAR 632-037-0145: Permit Modifications — authority
- OAR 632-037-0150: Civil Penalties — authority
- OAR 632-037-0155: Fees — authority
This rule cites
- ORS 517.952 — resolved
- 517.989 — resolved
- ORS 517.810 — resolved
- ORS 215.427 — resolved
- 227.178 — resolved
- 215.429 — resolved
- 227.179 — resolved
- ORS 197.015 — resolved
- ORS 517.750 — resolved
- 517.901 — resolved
- ORS 517.702 — resolved
Cited by
- ORS 517.825: Mining aggregate on high-value farmland; requirements; rules.
- ORS 517.832: Emergency operating permit; rules.
- ORS 517.834: Temporary operating permit; rules.
- ORS 517.837: Annual report by permittee; rules.
- OAR 632-030-0030: Department Action on Reclamation Plan and Operating Permit Application; Provisional Operating Permits; Local Government Actions
- OAR 632-030-0035: Modification of an Operating Permit
- OAR 632-035-0035: Modification of an Operating Permit