OAR 632-037-0095: Permitting Agency Action on a Consolidated Application
Edition: Current OARD snapshotEffective: 2014-04-02Last verified: 2026-09-07
(1) Within 225 days of the issuance of a Notice to Proceed and not sooner than 60 days after the submittal of a complete environmental evaluation, each permitting agency shall submit to the Department its draft permit and permit conditions or permit denial document. (2) If a permitting agency includes in its draft permit a condition that is inconsistent with the environmental evaluation, the agency shall include with its draft permits a written explanation of the conditions setting forth the findings of the agency that support the condition.
Official history and status
Statutory/Other Authority: ORS 517.750 - 517.995
Statutes/Other Implemented: ORS 517.978
History: DGMI 1-2014, f. & cert. ef. 4-2-14 GMI 2-1991, f. & cert. ef. 10-11-91
This rule cites
No citations extracted.
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/