ORS 537.690: Filing evidence, findings and determinations; court proceedings.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
The evidence relied upon by the Water Resources Director in the entry of the findings of fact and order of determination under ORS 537.685, together with a copy of such findings and order, shall be certified to by the director and filed with the clerk of the circuit court wherein the determination is to be heard, which shall be the circuit court of any county in which the ground water reservoir or any part thereof is located. A certified copy of the findings of fact and the order of determination shall also be filed with the county clerk of every other county in which the ground water reservoir or any part thereof is located. Thereafter, proceedings shall be had as nearly as possible in the same manner as provided in ORS 539.130 (2), (3) and (4), 539.150, 539.160, 539.170, 539.180, 539.190 and 539.210 for the final adjudication of the relative rights of the various claimants to the waters of any surface stream. [1955 c.708 §19]
Administrative rules citing this section
- OAR 690-013-0005: Introduction — implements
- OAR 690-013-0010: Definitions — implements
- OAR 690-013-0030: Eligibility to Petition — implements
- OAR 690-013-0050: Individual Applications — implements
- OAR 690-013-0070: Interim Transfers — implements
- OAR 690-013-0100: District Petitions — implements
- OAR 690-013-0110: Requests for Additional Information — implements
- OAR 690-013-0150: District Shall Certify Petition — implements
- OAR 690-013-0310: Processing of Petition — implements
- OAR 690-013-0350: Field Verification of the Petition and Map — implements
- OAR 690-190-0005: Purpose and Applicability — implements
- OAR 690-190-0010: Definitions — implements
- OAR 690-190-0010: Definitions — authority
- OAR 690-190-0100: Recording Requirements — implements
- OAR 690-190-0100: Recording Requirements — authority
- OAR 690-190-0200: Compliance and Enforcement — implements
- OAR 690-190-0200: Compliance and Enforcement — authority
- OAR 690-200-0005: Basis for Regulatory Authority — implements
- OAR 690-200-0005: Basis for Regulatory Authority — authority
- OAR 690-200-0020: General Statement About the Standards — implements
- OAR 690-200-0020: General Statement About the Standards — authority
- OAR 690-200-0021: Special Standards — implements
- OAR 690-200-0021: Special Standards — authority
- OAR 690-200-0027: Restrictions on Water Supply Well Construction and Use in Critical Groundwater Areas or Areas Withdrawn by Commission Order — implements
- OAR 690-200-0027: Restrictions on Water Supply Well Construction and Use in Critical Groundwater Areas or Areas Withdrawn by Commission Order — authority
- OAR 690-200-0028: Designated Special Area Standards — implements
- OAR 690-200-0028: Designated Special Area Standards — authority
- OAR 690-200-0046: Perched Ground Water — implements
- OAR 690-200-0046: Perched Ground Water — authority
- OAR 690-200-0050: Definitions — implements
- OAR 690-200-0050: Definitions — authority
- OAR 690-205-0005: License or Permit Required to Construct Water Supply Wells — implements
- OAR 690-205-0005: License or Permit Required to Construct Water Supply Wells — authority
- OAR 690-205-0010: Water Supply Well Constructor License Examination — implements
- OAR 690-205-0010: Water Supply Well Constructor License Examination — authority
- OAR 690-205-0020: Water Supply Well Constructor’s License, Experience Requirements, Trainee Card and Temporary Authorization — implements
- OAR 690-205-0020: Water Supply Well Constructor’s License, Experience Requirements, Trainee Card and Temporary Authorization — authority
- OAR 690-205-0025: Term of Water Well Constructor License and License Fees — implements
- OAR 690-205-0025: Term of Water Well Constructor License and License Fees — authority
- OAR 690-205-0045: Continuing Education Requirement — implements
- OAR 690-205-0045: Continuing Education Requirement — authority
- OAR 690-205-0175: Landowner Well Construction Permit, Fee and Bond — implements
- OAR 690-205-0175: Landowner Well Construction Permit, Fee and Bond — authority
- OAR 690-205-0200: Water Supply Well Construction Notice Required (Start Card) — implements
- OAR 690-205-0200: Water Supply Well Construction Notice Required (Start Card) — authority
- OAR 690-205-0205: Start Card Reporting Requirements — implements
- OAR 690-205-0205: Start Card Reporting Requirements — authority
- OAR 690-205-0210: Well Report Required (Water Supply Well Log) — implements
- OAR 690-205-0210: Well Report Required (Water Supply Well Log) — authority
- OAR 690-210-0130: Sealing of Wells in Unconsolidated Formations Without Significant Clay Beds — implements
- OAR 690-210-0130: Sealing of Wells in Unconsolidated Formations Without Significant Clay Beds — authority
- OAR 690-210-0140: Sealing of Water Supply Wells in Unconsolidated Formations with Significant Clay Beds — implements
- OAR 690-210-0140: Sealing of Water Supply Wells in Unconsolidated Formations with Significant Clay Beds — authority
- OAR 690-210-0150: Sealing of Water Supply Wells in Consolidated Formations — implements
- OAR 690-210-0150: Sealing of Water Supply Wells in Consolidated Formations — authority
- OAR 690-210-0155: Additional Standards for Artesian Water Supply Wells — implements
- OAR 690-210-0155: Additional Standards for Artesian Water Supply Wells — authority
- OAR 690-210-0160: Additional Standards for Filter Pack Wells with Surface Casing — implements
- OAR 690-210-0160: Additional Standards for Filter Pack Wells with Surface Casing — authority
- OAR 690-210-0170: Additional Standards for Filter Pack Wells without Surface Casing — implements
- OAR 690-210-0170: Additional Standards for Filter Pack Wells without Surface Casing — authority
- OAR 690-210-0180: Additional Standards for Driven or Jetted Wells — implements
- OAR 690-210-0180: Additional Standards for Driven or Jetted Wells — authority
- OAR 690-210-0190: Steel Casing — implements
- OAR 690-210-0190: Steel Casing — authority
- OAR 690-210-0220: Plastic Casing Joints — implements
- OAR 690-210-0220: Plastic Casing Joints — authority
- OAR 690-210-0230: Inner Casing — implements
- OAR 690-210-0230: Inner Casing — authority
- OAR 690-210-0240: Casing Shall be Centered — implements
- OAR 690-210-0240: Casing Shall be Centered — authority
- OAR 690-210-0270: Pitless Well Adapters and Units — implements
- OAR 690-210-0270: Pitless Well Adapters and Units — authority
- OAR 690-210-0280: Access Ports, Dedicated Measuring Tubes and Airlines — implements
- OAR 690-210-0280: Access Ports, Dedicated Measuring Tubes and Airlines — authority
- OAR 690-210-0290: Liner Pipe — implements
- OAR 690-210-0290: Liner Pipe — authority
- OAR 690-210-0320: Methods of Placement of Cement Grout or Concrete — implements
- OAR 690-210-0320: Methods of Placement of Cement Grout or Concrete — authority
- OAR 690-210-0380: Disinfection of a Well — implements
- OAR 690-210-0380: Disinfection of a Well — authority
- OAR 690-210-0400: Construction of Dug Wells — implements
- OAR 690-210-0400: Construction of Dug Wells — authority
- OAR 690-210-0410: Buried Slab Construction — implements
- OAR 690-210-0410: Buried Slab Construction — authority
- OAR 690-210-0420: Surface Curbing — implements
- OAR 690-210-0420: Surface Curbing — authority
- OAR 690-215-0005: Prevention of Groundwater Contamination, Health Hazard, and Waste — implements
- OAR 690-215-0005: Prevention of Groundwater Contamination, Health Hazard, and Waste — authority
- OAR 690-215-0017: Down Well Continuous Water Treatment and Back-Siphon Prevention Devices — implements
- OAR 690-215-0017: Down Well Continuous Water Treatment and Back-Siphon Prevention Devices — authority
- OAR 690-215-0055: Well Identification Label Maintenance — implements
- OAR 690-215-0055: Well Identification Label Maintenance — authority
- OAR 690-215-0060: Access Ports, Dedicated Measuring Tubes and Airlines — implements
- OAR 690-215-0060: Access Ports, Dedicated Measuring Tubes and Airlines — authority
- OAR 690-215-0070: Pressure Gauge — implements
- OAR 690-215-0070: Pressure Gauge — authority
- OAR 690-215-0201: Dedicated Measuring Tube — implements
- OAR 690-215-0201: Dedicated Measuring Tube — authority
- OAR 690-220-0050: Abandonment of Uncased Wells — implements
- OAR 690-220-0050: Abandonment of Uncased Wells — authority
- OAR 690-225-0020: Investigation of Alleged Violations — implements
- OAR 690-225-0020: Investigation of Alleged Violations — authority
- OAR 690-225-0030: Enforcement Actions — implements
- OAR 690-225-0030: Enforcement Actions — authority
- OAR 690-225-0110: Schedule of Civil Penalties — implements
- OAR 690-225-0110: Schedule of Civil Penalties — authority
- OAR 690-240-0005: Introduction — implements
- OAR 690-240-0005: Introduction — authority
- OAR 690-240-0006: Special Standards — implements
- OAR 690-240-0006: Special Standards — authority
- OAR 690-240-0010: Definitions — implements
- OAR 690-240-0010: Definitions — authority
- OAR 690-240-0024: Well Identification Label — implements
- OAR 690-240-0024: Well Identification Label — authority
- OAR 690-240-0026: Well Identification Label Maintenance — implements
- OAR 690-240-0026: Well Identification Label Maintenance — authority
- OAR 690-240-0060: Monitoring Well Constructor License Examination — implements
- OAR 690-240-0060: Monitoring Well Constructor License Examination — authority
- OAR 690-240-0065: Monitoring Well Constructor License, Experience Requirements, Trainee Card and Temporary Authorization — implements
- OAR 690-240-0065: Monitoring Well Constructor License, Experience Requirements, Trainee Card and Temporary Authorization — authority
- OAR 690-240-0070: Terms of Monitoring Well Constructor License and License Fees — implements
- OAR 690-240-0070: Terms of Monitoring Well Constructor License and License Fees — authority
- OAR 690-240-0210: Continuing Education Requirement — implements
- OAR 690-240-0210: Continuing Education Requirement — authority
- OAR 690-240-0340: Landowner Well Construction Permit, Fee and Bond — authority
- OAR 690-240-0375: Monitoring Well Construction Notice Required (Start Card) — implements
- OAR 690-240-0375: Monitoring Well Construction Notice Required (Start Card) — authority
- OAR 690-240-0385: Start Card Reporting Requirements — implements
- OAR 690-240-0385: Start Card Reporting Requirements — authority
- OAR 690-240-0395: Monitoring Well Report Required (Monitoring Well Log) — implements
- OAR 690-240-0395: Monitoring Well Report Required (Monitoring Well Log) — authority
- OAR 690-240-0410: Monitoring Well Construction: General — implements
- OAR 690-240-0410: Monitoring Well Construction: General — authority
- OAR 690-240-0560: Investigation of Alleged Violations — implements
- OAR 690-240-0560: Investigation of Alleged Violations — authority
- OAR 690-240-0580: Enforcement Actions — implements
- OAR 690-240-0580: Enforcement Actions — authority
- OAR 690-240-0640: Schedule of Civil Penalties — implements
- OAR 690-240-0640: Schedule of Civil Penalties — authority
- OAR 690-260-0030: Notice of Violation — implements
- OAR 690-260-0030: Notice of Violation — authority
- OAR 690-260-0040: Classification of Violations — implements
- OAR 690-260-0040: Classification of Violations — authority
- OAR 690-260-0060: Notice of Assessment of Civil Penalty — implements
- OAR 690-260-0060: Notice of Assessment of Civil Penalty — authority
- OAR 690-300-0010: Definitions — authority
- OAR 690-410-0070: Water Allocation — authority
This rule cites
- ORS 537.685 — resolved
- ORS 539.130 — resolved
Cited by
No inbound citations found.
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors537.html