ORS 537.153: Review of application; proposed final order; presumption that use will not impair or be detrimental to public interest; standing; protest; final order; contested case hearing.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) Within 60 days after the Water Resources Department proceeds with the application under ORS 537.150 (5)(c), the department shall complete application review and issue a proposed final order approving or denying the application or approving the application with modifications or conditions. The department may request the applicant to provide additional information needed to complete the review. If the department requests additional information, the request shall be specific and shall be sent to the applicant by registered mail. The department shall specify a date by which the information must be returned, which shall be not less than 10 days after the department mails the request to the applicant. If the department does not receive the information or a request for a time extension under ORS 537.175 by the date specified in the request, the department may reject the application and may refund fees in accordance with ORS 536.050 (4)(a). The time period specified by the department in a request for additional information shall allow the department to comply with the 60-day time limit established by this subsection. (2) In reviewing the application under subsection (1) of this section, the department shall presume that a proposed use will not impair or be detrimental to the public interest if the proposed use is allowed in the applicable basin program established pursuant to ORS 536.300 and 536.340 or given a preference under ORS 536.310 (12), if water is available, if the proposed use will not injure other water rights and if the proposed use complies with rules of the Water Resources Commission. This shall be a rebuttable presumption and may be overcome by a preponderance of evidence that either: (a) One or more of the criteria for establishing the presumption are not satisfied; or (b) The proposed use will impair or be detrimental to the public interest as demonstrated in comments, in a protest under ORS 536.077 or in a finding of the department that shows: (A) The specific public interest under ORS 537.170 (7) that would be impaired or detrimentally affected; and (B) Specifically how the identified public interest would be impaired or detrimentally affected. (3) The proposed final order shall cite findings of fact and conclusions of law and shall include but need not be limited to: (a) Confirmation or modification of the preliminary determinations made in the initial review; (b) A brief statement that explains the criteria considered relevant to the decision, including the applicable basin program and the compatibility of the proposed use with applicable land use plans; (c) An assessment of water availability and the amount of water necessary for the proposed use; (d) An assessment of whether the proposed use would result in injury to existing water rights; (e) An assessment of whether the proposed use would impair or be detrimental to the public interest as provided in ORS 537.170; (f) A draft permit, including any proposed conditions, or a recommendation to deny the application; (g) Whether the rebuttable presumption that the proposed use will not impair or be detrimental to the public interest has been established; and (h) The date by which protests to the proposed final order must be received by the department. (4) The department shall mail copies of the proposed final order to the applicant and to persons who have requested copies and paid the fee required under ORS 536.050 (1)(p). The department also shall publish notice of the proposed final order by publication in the weekly public notice published by the department. (5) A person who asks to receive a copy of the department’s final order shall submit to the department the fee required under ORS 536.050 (1)(p), unless the person has previously requested copies and has paid the fee required under ORS 537.150 (6), the person is a protestant and has paid the fee required under ORS 536.050 (1)(j) or the person has party status and has paid the fees required under ORS 536.050 (1)(n) and (o). (6) The provisions of ORS 536.076 and 536.077, and rules adopted thereunder, apply to a contested case proceeding on a proposed final order issued under this section. (7) Within 60 days after the close of the period for receiving protests, if a protest was timely submitted, the Water Resources Director shall: (a) Issue a final order as provided under ORS 537.170 (1) or (2), if the applicant has not filed a protest and the director finds that there are no significant issues related to the proposed use of water; (b) Schedule a contested case hearing if a protest has been submitted; or (c) Provide any person who timely submitted a protest or request for party status with an estimate of the timing of referring the contested case to the Office of Administrative Hearings for a hearing and notice that parties may provide settlement proposals. [1995 c.416 §11; 1997 c.446 §2; 1997 c.587 §5; 2007 c.188 §2; 2009 c.819 §§7,14; 2013 c.644 §5; 2025 c.575 §§5,5a] 537.153. (1) Within 60 days after the Water Resources Department proceeds with the application under ORS 537.150 (5), the department shall complete application review and issue a proposed final order approving or denying the application or approving the application with modifications or conditions. The department may request the applicant to provide additional information needed to complete the review. If the department requests additional information, the request shall be specific and shall be sent to the applicant by registered mail. The department shall specify a date by which the information must be returned, which shall be not less than 10 days after the department mails the request to the applicant. If the department does not receive the information or a request for a time extension under ORS 537.175 by the date specified in the request, the department may reject the application and may refund fees in accordance with ORS 536.050 (4)(a). The time period specified by the department in a request for additional information shall allow the department to comply with the 60-day time limit established by this subsection. (2) In reviewing the application under subsection (1) of this section, the department shall presume that a proposed use will not impair or be detrimental to the public interest if the proposed use is allowed in the applicable basin program established pursuant to ORS 536.300 and 536.340 or given a preference under ORS 536.310 (12), if water is available, if the proposed use will not injure other water rights and if the proposed use complies with rules of the Water Resources Commission. This shall be a rebuttable presumption and may be overcome by a preponderance of evidence that either: (a) One or more of the criteria for establishing the presumption are not satisfied; or (b) The proposed use will impair or be detrimental to the public interest as demonstrated in comments, in a protest under ORS 536.077 or in a finding of the department that shows: (A) The specific public interest under ORS 537.170 (7) that would be impaired or detrimentally affected; and (B) Specifically how the identified public interest would be impaired or detrimentally affected. (3) The proposed final order shall cite findings of fact and conclusions of law and shall include but need not be limited to: (a) Confirmation or modification of the preliminary determinations made in the initial review; (b) A brief statement that explains the criteria considered relevant to the decision, including the applicable basin program and the compatibility of the proposed use with applicable land use plans; (c) An assessment of water availability and the amount of water necessary for the proposed use; (d) An assessment of whether the proposed use would result in injury to existing water rights; (e) An assessment of whether the proposed use would impair or be detrimental to the public interest as provided in ORS 537.170; (f) A draft permit, including any proposed conditions, or a recommendation to deny the application; (g) Whether the rebuttable presumption that the proposed use will not impair or be detrimental to the public interest has been established; and (h) The date by which protests to the proposed final order must be received by the department. (4) The department shall mail copies of the proposed final order to the applicant and to persons who have requested copies and paid the fee required under ORS 536.050 (1)(p). The department also shall publish notice of the proposed final order by publication in the weekly notice published by the department. (5) A person who asks to receive a copy of the department’s final order shall submit to the department the fee required under ORS 536.050 (1)(p), unless the person has previously requested copies and has paid the fee required under ORS 537.150 (7), the person is a protestant and has paid the fee required under ORS 536.050 (1)(j) or the person has party status and has paid the fees required under ORS 536.050 (1)(n) and (o). (6) The provisions of ORS 536.076 and 536.077, and rules adopted thereunder, apply to a contested case proceeding on a proposed final order issued under this section. (7) Within 60 days after the close of the period for receiving protests, if a protest was timely submitted, the Water Resources Director shall: (a) Issue a final order as provided under ORS 537.170 (1) or (2), if the applicant has not filed a protest and the director finds that there are no significant issues related to the proposed use of water; (b) Schedule a contested case hearing if a protest has been submitted; or (c) Provide any person who timely submitted a protest or request for party status with an estimate of the timing of referring the contested case to the Office of Administrative Hearings for a hearing and notice that parties may provide settlement proposals.
Official history and status
History: Note: The amendments to 537.153 by section 5a, chapter 575, Oregon Laws 2025, become operative April 1, 2026, and apply to requests for standing on proposed final orders issued on or after April 1, 2026. See section 33a, chapter 282, Oregon Laws 2025, as amended by section 16b, chapter 575, Oregon Laws 2025, and see section 48, chapter 282, Oregon Laws 2025, as amended by section 21c, chapter 575, Oregon Laws 2025. The text that is operative until April 1, 2026, including amendments by section 5, chapter 575, Oregon Laws 2025, is set forth for the user’s convenience. Note: 537.153, 537.173 and 537.175 were added to and made a part of 537.145 to 537.240 by legislative action but were not added to any smaller series therein. See Preface to Oregon Revised Statutes for further explanation.
Administrative rules citing this section
- OAR 690-033-0120: Upper Columbia Rules (Above Bonneville Dam): Determination of Consistency With the Fish and Wildlife Program — implements
- OAR 690-033-0130: Upper Columbia Rules (Above Bonneville Dam): Flow Management — implements
- OAR 690-033-0140: Upper Columbia Rules (Above Bonneville Dam): Exemptions — implements
- OAR 690-033-0210: Lower Columbia Rules (Below Bonneville Dam): Geographic Scope — implements
- OAR 690-033-0310: Statewide Rules: Geographic Scope — implements
- OAR 690-033-0320: Statewide Rules: Rule Review — implements
- OAR 690-033-0330: Statewide Rules: Review of Proposed Water Use — implements
- OAR 690-033-0340: Statewide Rules: Public Interest Review Presumption — implements
- OAR 690-077-0019: State Agency Instream Water Right Applications: Process for Instream Water Right Certificate Requests — authority
- OAR 690-077-0020: State Agency Instream Water Right Applications: Application Requirements — authority
- OAR 690-077-0033: Application Processing: Public Interest Presumption — authority
- OAR 690-077-0037: Application Processing: Public Interest Review — authority
- OAR 690-077-0039: Application Processing: Proposed Final Order — implements
- OAR 690-077-0039: Application Processing: Proposed Final Order — authority
- OAR 690-077-0043: Application Processing: Protests and Conduct of Contested Case; Final Orders on Default when No Protest Filed — implements
- OAR 690-077-0043: Application Processing: Protests and Conduct of Contested Case; Final Orders on Default when No Protest Filed — authority
- OAR 690-077-0047: Application Processing: Final Orders — implements
- OAR 690-077-0051: Application Processing: Contested Case Hearing on Final Order that Modifies Proposed Final Order — implements
- OAR 690-310-0000: Purpose — implements
- OAR 690-310-0100: Completion of Application Review; Additional Information and Proposed Final Order — implements
- OAR 690-310-0110: Public Interest Presumption; Surface Water — implements
- OAR 690-310-0120: Public Interest Review; Surface Water — implements
- OAR 690-310-0150: Proposed Final Order — implements
- OAR 690-310-0160: Protests and Conduct of Contested Case; Final Orders on Default when No Protest Filed — implements
- OAR 690-310-0190: Final Order for Proposed Use of Surface Water when Proposed Final Order Protested — implements
- OAR 690-310-0210: Contested Case Hearing on Final Order that Modifies Proposed Final Order — implements
This rule cites
- ORS 537.150 — resolved
- ORS 537.175 — resolved
- ORS 536.050 — resolved
- ORS 536.300 — resolved
- 536.340 — resolved
- ORS 536.310 — resolved
- ORS 536.077 — resolved
- ORS 537.170 — resolved
- ORS 536.076 — resolved
- 536.077 — resolved
Cited by
- ORS 537.147: Permit to use stored water; fee.
- ORS 537.170: Protest of proposed final order; final order; appeal.
- OAR 690-077-0047: Application Processing: Final Orders
- OAR 690-077-0051: Application Processing: Contested Case Hearing on Final Order that Modifies Proposed Final Order
- OAR 690-310-0190: Final Order for Proposed Use of Surface Water when Proposed Final Order Protested
- OAR 690-310-0210: Contested Case Hearing on Final Order that Modifies Proposed Final Order
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors537.html