ORS 517.986: Time limit for final action on permit subject to consolidated application process.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
Notwithstanding any other provision of law, the State Department of Geology and Mineral Industries and any other permitting agency shall take final action to issue or deny a permit subject to the consolidated application process set forth in ORS 517.952 to 517.989 within one year after issuance of a notice to proceed under ORS 517.977. However, with the concurrence of the applicant, the processing of the application may be suspended for a period of time to allow the applicant to resolve issues having a bearing on, or necessary to any permitting agency’s decision or the department’s decision on whether to issue or deny a permit. [1991 c.735 §24]
Administrative rules citing this section
- OAR 632-030-0026: On-Site Construction Waiver — implements
- OAR 632-030-0041: Permit and Exemption Transfer — implements
- OAR 632-030-0049: Emergency Operating Permits — implements
- OAR 632-030-0052: Temporary Operating Permits — implements
- OAR 632-037-0005: Purpose — implements
- OAR 632-037-0005: Purpose — authority
- OAR 632-037-0010: Definitions — authority
- OAR 632-037-0015: State and Federal Agency Coordination — authority
- OAR 632-037-0020: Project Coordinating Committee — authority
- OAR 632-037-0025: Technical Review Team — authority
- OAR 632-037-0030: Public Notice Procedure — authority
- OAR 632-037-0035: Notice of Intent — authority
- OAR 632-037-0040: Notice of Prospective Applicant’s Readiness to Collect Baseline Data — authority
- OAR 632-037-0045: Content — authority
- OAR 632-037-0050: General Information — authority
- OAR 632-037-0055: Existing Environment — Baseline Data — authority
- OAR 632-037-0060: Operating Plan — authority
- OAR 632-037-0070: Reclamation and Closure Plan — authority
- OAR 632-037-0075: Alternatives Analysis — authority
- OAR 632-037-0077: Additional Requirements — authority
- OAR 632-037-0080: Notice to Proceed — authority
- OAR 632-037-0085: Environmental Evaluation — authority
- OAR 632-037-0090: Socioeconomic Impact Analysis — authority
- OAR 632-037-0095: Permitting Agency Action on a Consolidated Application — authority
- OAR 632-037-0100: Cooperating Agency Action on a Consolidated Application — authority
- OAR 632-037-0105: Consolidated Public Hearing; Final Permits — authority
- OAR 632-037-0110: Appeals; Consolidated Contested Case Hearing — authority
- OAR 632-037-0115: Judicial Review — authority
- OAR 632-037-0118: Best Available Practicable and Necessary Technology — authority
- OAR 632-037-0120: Mine Operation Standards — authority
- OAR 632-037-0125: Fish and Wildlife Standards — authority
- OAR 632-037-0130: Reclamation and Mine Closure Standards — authority
- OAR 632-037-0135: Financial Security — authority
- OAR 632-037-0140: Obtaining Financial Security Release — authority
- OAR 632-037-0145: Permit Modifications — authority
- OAR 632-037-0150: Civil Penalties — authority
- OAR 632-037-0155: Fees — authority
- OAR 690-310-0040: Application Requirements — implements
This rule cites
- ORS 517.952 — resolved
- 517.989 — resolved
- ORS 517.977 — resolved
Cited by
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors517.html