ORS 517.865: Effect of failure to perform reclamation and insufficient bond; lien; notice; priority; foreclosure.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) If an operator fails to faithfully perform the reclamation required by the reclamation plan and if the bond or security required by ORS 517.810 is not sufficient to compensate the State Department of Geology and Mineral Industries for all reasonably necessary costs and expenses incurred by it in reclaiming the surface-mined land, the amount due shall be a lien in favor of the department upon all property, whether real or personal, belonging to the operator. However, for any operator that is first issued a permit after June 30, 1989, the lien shall not exceed $2,500 for each site plus $1,500 per acre. (2) The lien shall attach upon the filing of a notice of claim of lien with the county clerk of the county in which the property is located. The notice of lien claim shall contain a true statement of the demand, the insufficiency of the bond or security to compensate the department and the failure of the operator to perform the reclamation required. (3) The lien created by this section is prior to all other liens and encumbrances, except that the lien shall have equal priority with tax liens. (4) The lien created by this section may be foreclosed by a suit in the circuit court in the manner provided by law for the foreclosure of other liens on real or personal property. [1975 c.724 §8; 1983 c.497 §3; 1985 c.291 §4; 1987 c.361 §7; 1999 c.492 §6; 2007 c.318 §19]
Administrative rules citing this section
- OAR 632-030-0026: On-Site Construction Waiver — implements
- OAR 632-030-0041: Permit and Exemption Transfer — implements
- OAR 632-030-0049: Emergency Operating Permits — implements
- OAR 632-030-0052: Temporary Operating Permits — implements
- OAR 632-037-0005: Purpose — implements
- OAR 632-037-0005: Purpose — authority
- OAR 632-037-0010: Definitions — authority
- OAR 632-037-0015: State and Federal Agency Coordination — authority
- OAR 632-037-0020: Project Coordinating Committee — authority
- OAR 632-037-0025: Technical Review Team — authority
- OAR 632-037-0030: Public Notice Procedure — authority
- OAR 632-037-0035: Notice of Intent — authority
- OAR 632-037-0040: Notice of Prospective Applicant’s Readiness to Collect Baseline Data — authority
- OAR 632-037-0045: Content — authority
- OAR 632-037-0050: General Information — authority
- OAR 632-037-0055: Existing Environment — Baseline Data — authority
- OAR 632-037-0060: Operating Plan — authority
- OAR 632-037-0070: Reclamation and Closure Plan — authority
- OAR 632-037-0075: Alternatives Analysis — authority
- OAR 632-037-0077: Additional Requirements — authority
- OAR 632-037-0080: Notice to Proceed — authority
- OAR 632-037-0085: Environmental Evaluation — authority
- OAR 632-037-0090: Socioeconomic Impact Analysis — authority
- OAR 632-037-0095: Permitting Agency Action on a Consolidated Application — authority
- OAR 632-037-0100: Cooperating Agency Action on a Consolidated Application — authority
- OAR 632-037-0105: Consolidated Public Hearing; Final Permits — authority
- OAR 632-037-0110: Appeals; Consolidated Contested Case Hearing — authority
- OAR 632-037-0115: Judicial Review — authority
- OAR 632-037-0118: Best Available Practicable and Necessary Technology — authority
- OAR 632-037-0120: Mine Operation Standards — authority
- OAR 632-037-0125: Fish and Wildlife Standards — authority
- OAR 632-037-0130: Reclamation and Mine Closure Standards — authority
- OAR 632-037-0135: Financial Security — authority
- OAR 632-037-0140: Obtaining Financial Security Release — authority
- OAR 632-037-0145: Permit Modifications — authority
- OAR 632-037-0150: Civil Penalties — authority
- OAR 632-037-0155: Fees — authority
This rule cites
- ORS 517.810 — resolved
Cited by
No inbound citations found.
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors517.html