ORS 517.790: Operating permit required for surface mining on certain lands; application for permit; proposed reclamation plans; waiver of requirement for preparation and approval of reclamation plan; refusal to issue operating permit; provisional operating permit.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) A landowner or operator may not allow or engage in surface mining on land not surface mined on July 1, 1972, without holding a valid operating permit from the State Department of Geology and Mineral Industries for the surface mining operation. A separate permit is required for each separate surface mining operation. A person seeking an operating permit from the department shall submit an application on a form provided by the department that contains the following information: (a) The name and address of the landowner and the operator and the names and addresses of any persons designated by them as their agents for the service of process. (b) The materials for which the operation is to be conducted. (c) The type of surface mining to be employed in the operation. (d) The proposed date for the initiation of the operation. (e) The size and legal description of the lands that will be affected by the operation, and, if more than 10 acres of land will be affected by the operation and if the department determines that the conditions warrant it, a map of the lands to be surface mined that includes the boundaries of the affected lands, topographic details of the lands, the location and names of all streams, roads, railroads, utility facilities, wells, irrigation ditches, ponds, stockpiles, buffers, setbacks and excavation boundaries within or adjacent to the lands, the location of all proposed access roads to be protected or constructed in conducting the operation and the names and addresses of the owners of all surface and mineral interests of the lands included within the surface mining area. (f) If practicable, a plan for visual screening by vegetation or otherwise that will be established and maintained on the lands within the operation for the purpose of screening the operation from the view of persons using adjacent public highways, public parks and residential areas. (g) The type of monitoring well abandonment procedures. (h) A proposed reclamation plan that is acceptable to and approved by the department. (i) Any other information that the department considers pertinent in its review of the application. (2) The department may waive the requirement for preparation and approval of a reclamation plan if: (a) The operation is conducted as part of the on-site construction of a building, public works project or other physical improvement of the subject property; (b) The operation is reasonably necessary for such construction; and (c) The proposed improvements are authorized by the local jurisdiction with land use authority. (3) The department may not issue an operating permit to an operator other than the owner or owners of the surface and mineral interests of the lands included within the surface mining area unless the operator: (a) Has written approval from the owner or owners of all surface and mineral interests of the lands included within the surface mining area; and (b) Maintains a legal interest in the lands that is sufficient to ensure that the operator has the authority to operate and reclaim the lands as provided in the operating permit and reclamation plan. (4) The department may refuse to issue an operating permit to a person who has not, in the determination of the department, substantially complied with the conditions of an operating permit or reclamation plan, the provisions of this chapter or the rules adopted by the department to carry out the purposes of this chapter. (5) The department shall issue a provisional operating permit to an applicant that has not obtained all required federal, state and local permits and approvals for the proposed mining operation, provided: (a) The applicant has complied with this chapter and the rules adopted by the department to carry out the purposes of this chapter; and (b) The permit: (A) Does not become effective until the applicant obtains all required permits and approvals; and (B) Contains conditions: (i) Requiring the applicant to obtain an amendment to the provisional operating permit if necessary to conform with a subsequently obtained federal, state or local permit or approval; and (ii) Prohibiting the applicant from allowing or engaging in any surface mining operations on the land prior to the effective date of the provisional operating permit. [1971 c.719 §4; 1973 c.709 §2; 1987 c.361 §10; 1989 c.347 §10; 1999 c.353 §3; 2007 c.318 §7; 2017 c.736 §3]
Administrative rules citing this section
- OAR 340-043-0030: Permit Application — implements
- OAR 632-030-0020: Procedures for Applying for an Operating Permit — implements
- OAR 632-030-0025: Requirements for an Operating Permit and Reclamation Plan — implements
- OAR 632-030-0026: On-Site Construction Waiver — implements
- OAR 632-030-0030: Department Action on Reclamation Plan and Operating Permit Application; Provisional Operating Permits; Local Government Actions — implements
- OAR 632-030-0041: Permit and Exemption Transfer — implements
- OAR 632-030-0049: Emergency Operating Permits — implements
- OAR 632-030-0052: Temporary Operating Permits — implements
- OAR 632-035-0020: Procedures for Applying for an Operating Permit — implements
- OAR 632-037-0005: Purpose — implements
- OAR 632-037-0005: Purpose — authority
- OAR 632-037-0010: Definitions — authority
- OAR 632-037-0015: State and Federal Agency Coordination — authority
- OAR 632-037-0020: Project Coordinating Committee — authority
- OAR 632-037-0025: Technical Review Team — authority
- OAR 632-037-0030: Public Notice Procedure — authority
- OAR 632-037-0035: Notice of Intent — authority
- OAR 632-037-0040: Notice of Prospective Applicant’s Readiness to Collect Baseline Data — authority
- OAR 632-037-0045: Content — authority
- OAR 632-037-0050: General Information — authority
- OAR 632-037-0055: Existing Environment — Baseline Data — authority
- OAR 632-037-0060: Operating Plan — authority
- OAR 632-037-0070: Reclamation and Closure Plan — authority
- OAR 632-037-0075: Alternatives Analysis — authority
- OAR 632-037-0077: Additional Requirements — authority
- OAR 632-037-0080: Notice to Proceed — authority
- OAR 632-037-0085: Environmental Evaluation — authority
- OAR 632-037-0090: Socioeconomic Impact Analysis — authority
- OAR 632-037-0095: Permitting Agency Action on a Consolidated Application — authority
- OAR 632-037-0100: Cooperating Agency Action on a Consolidated Application — authority
- OAR 632-037-0105: Consolidated Public Hearing; Final Permits — authority
- OAR 632-037-0110: Appeals; Consolidated Contested Case Hearing — authority
- OAR 632-037-0115: Judicial Review — authority
- OAR 632-037-0118: Best Available Practicable and Necessary Technology — authority
- OAR 632-037-0120: Mine Operation Standards — authority
- OAR 632-037-0125: Fish and Wildlife Standards — authority
- OAR 632-037-0130: Reclamation and Mine Closure Standards — authority
- OAR 632-037-0135: Financial Security — authority
- OAR 632-037-0140: Obtaining Financial Security Release — authority
- OAR 632-037-0145: Permit Modifications — authority
- OAR 632-037-0150: Civil Penalties — authority
- OAR 632-037-0155: Fees — authority
This rule cites
No citations extracted.
Cited by
- ORS 517.702: Legislative findings.
- ORS 517.720: Persons with operating permit exempted.
- ORS 517.725: Department inspection of exploration site.
- ORS 517.740: Rules.
- ORS 517.750: Definitions for ORS 517.702 to 517.989.
- ORS 517.780: Effect on county zoning laws or ordinances; rules; certain operations exempt.
- ORS 517.795: Department to consult with and cooperate with other agencies.
- ORS 517.800: Fees; rules; annual report.
- ORS 517.820: Extensions of time for submission of proposed reclamation plans; time limit for reclamation completion; consultation with cooperating agencies.
- ORS 517.825: Mining aggregate on high-value farmland; requirements; rules.
- ORS 517.971: Consolidated application.
- ORS 517.973: Fees; payment of expenses of department and permitting and cooperating agencies.
- OAR 632-030-0017: Limited Exemption
- OAR 632-030-0025: Requirements for an Operating Permit and Reclamation Plan
- OAR 632-030-0026: On-Site Construction Waiver
- OAR 632-033-0016: Exemptions
- OAR 632-035-0010: Definitions
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors517.html