ORS 374.360: Access Management Dispute Review Board.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) If the applicant or permit holder of an approach permit requests a review by an Access Management Dispute Review Board under ORS 374.355, the Department of Transportation shall appoint an Access Management Dispute Review Board by selecting members for a board consisting of any or all of following: (a) The Director of Transportation or a designee of the director who is familiar with the location in which the disputed approach is located. (b) A representative of the local jurisdiction in which the disputed approach is located. (c) A traffic engineer who practices engineering in Oregon. (d) A representative from the economic or business sector. (2) The Access Management Dispute Review Board shall consider information presented by the parties and shall notify the applicant or permit holder and the director of its findings regarding the department’s original decision. (3) The director shall review the Access Management Dispute Review Board’s findings and may approve, modify or reverse the department’s original decision to approve an application for an approach permit with conditions, to modify or require mitigation measures for an existing approach permit, to deny the approach permit or to remove or modify an approach. (4) The director shall notify the applicant or permit holder in writing of the department’s determination following a review by an Access Management Dispute Review Board appointed under this section. [2011 c.330 §15] RIGHTS APPURTENANT TO PROPERTY ABUTTING CERTAIN HIGHWAYS AND ROADS
Administrative rules citing this section
- OAR 734-051-1010: Authority for Rules — General Provisions — implements
- OAR 734-051-1020: Purpose and Intent of Rules — implements
- OAR 734-051-1030: Administration of Rules — implements
- OAR 734-051-1040: Relationship to Local Jurisdiction Rules and Regulations — implements
- OAR 734-051-1050: Procedure to Obtain a Permit to Construct or Modify a Public Approach — implements
- OAR 734-051-1060: Delegation of Permit Authority to Local Jurisdiction — implements
- OAR 734-051-1070: Definitions — implements
- OAR 734-051-2010: Rights of Access — General Provisions — implements
- OAR 734-051-2020: Grants of Access — implements
- OAR 734-051-2030: Indentures of Access — implements
- OAR 734-051-3010: Administration of Private Approaches — Permit for Private Approach — implements
- OAR 734-051-3015: Presumption of Written Permission for an Existing Private Connection — implements
- OAR 734-051-3020: Change of Use of a Private Connection — implements
- OAR 734-051-3030: Application Requirements for State Highway Private Approach — implements
- OAR 734-051-3040: Private Approach Permit Application Review, Approvals and Timelines — implements
- OAR 734-051-3050: Deviations from Approach Spacing, Sight Distance, and Channelization Standards for a Private Approach — implements
- OAR 734-051-3060: Pre-Decision Collaborative Discussion for Highway Approach Permit Applications — implements
- OAR 734-051-3070: Mitigation Measures — implements
- OAR 734-051-3080: Post-Decision Review Processes — implements
- OAR 734-051-3090: Post-Decision Collaborative Discussion — implements
- OAR 734-051-3100: Access Management Dispute Review Board — implements
- OAR 734-051-3110: Contested Case Hearing Process — implements
- OAR 734-051-4010: Access Management Standards for Approaches — General Provisions — implements
- OAR 734-051-4020: Standards and Criteria for Approval of Private Approaches — implements
- OAR 734-051-4030: Benefit to the State Highway System — implements
- OAR 734-051-4040: Temporary Approaches — implements
- OAR 734-051-4050: Special Use Approaches — implements
- OAR 734-051-5010: Approach Design and Construction — Design of Approaches — implements
- OAR 734-051-5020: Issuance of Construction Permits — implements
- OAR 734-051-5030: Construction of Approaches — implements
- OAR 734-051-5040: Effective Period of Construction Permits — implements
- OAR 734-051-5050: Responsibility for Costs of Construction of Approaches — implements
- OAR 734-051-5060: Liability, Insurance and Bonding Requirements — implements
- OAR 734-051-5070: Review Procedure for Modifying a Construction Permit — implements
- OAR 734-051-5080: Issuance of a Permit to Operate, Maintain and Use an Approach — implements
- OAR 734-051-5090: Maintenance of Approaches — implements
- OAR 734-051-5100: Effective Period of Permit to Operate, Maintain and Use an Approach — implements
- OAR 734-051-5110: Revocation of Permits and Removal of Approaches — implements
- OAR 734-051-5120: Access Management in Project Delivery — implements
- OAR 734-051-6010: Remedies in Closure of Approaches — Authority and Purpose of OAR 734-051-6010 through 734-051-6060 — implements
- OAR 734-051-6020: Definitions — implements
- OAR 734-051-6030: Offer of Remedies — implements
- OAR 734-051-6040: Procedure for Resolving Claims — implements
- OAR 734-051-6050: Appraisals — implements
- OAR 734-051-6060: Conditions of Agreement — implements
- OAR 734-051-6070: Delegation — implements
- OAR 734-051-7010: Access Management in Highway Facility Plans — implements
This rule cites
- ORS 374.355 — resolved
Cited by
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors374.html