OAR 734-051-5070: Review Procedure for Modifying a Construction Permit
Edition: Current OARD snapshotEffective: 2012-06-29Last verified: 2026-09-07
(1) Review. An applicant may request a review to modify a construction permit if: (a) Ambiguities or conflicts exist in the construction permit; (b) New and relevant information concerning the approach or the construction permit is available; or (c) Requirements of local governments or state agencies are relevant to the modification of the construction permit. (2) Procedure. (a) The region manager shall determine if a request to review a construction permit meets the criteria in section (1) of this rule. (b) If the region manager determines that the criteria in section (1) are met, the region manager shall review and may modify the construction permit in cooperation with affected parties and consistent with engineering best practices.
Official history and status
Statutory/Other Authority: ORS 184.616, 184.619, 374.310–374.314, 374.345 & 374.355
Statutes/Other Implemented: ORS 374.300–374.360, §27, ch. 330 & OL 2011
History: HWD 8-2012, f. 6-27-12, cert. ef. 6-29-12 HWD 16-2011(Temp), f. 12-22-11, cert. ef. 1-1-12 thru 6-29-12
This rule cites
- section (1) of this rule — target_record_not_published
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/