OAR 806-010-0050: Observation
Edition: Current OARD snapshotEffective: 2024-01-02Last verified: 2026-09-07
(1) Construction phase services that constitute the practice of architecture include but are not limited to: (a) Clarification and modification of technical submissions during the construction phase; and (b) Observing the construction site through substantial completion to determine that the work is proceeding generally in accordance with the technical submission. (2) With the exception of exempt projects, construction phase services that constitute the practice of architecture must be performed by an architect, or under an architect's responsible control. (3) If the architect, or the architect's firm, that stamped technical submissions to be used for construction of a non exempt project will not provide construction phase services described in OAR 806-010-0050(1), the architect must so advise the governmental authority that issued a permit for construction and the Board in writing within 10 days of when the architect becomes aware that they will not provide the construction phase services. This written notice must also include the project address and project owner’s name.
Official history and status
Statutory/Other Authority: ORS 670.310, 671.010 & 671.125
Statutes/Other Implemented: ORS 671.010 – 671.220/SB 224 (2023)
History: BAE 3-2023, amend filed 10/10/2023, effective 01/02/2024 BAE 3-2019, amend filed 12/20/2019, effective 02/01/2020 BAE 2-2019, amend filed 04/10/2019, effective 05/01/2019 BAE 7-2014, f. & cert. ef. 10-23-14 BAE 3-2005, f. & cert. ef. 5-12-05 BAE 1-1999, f. & cert. ef. 3-25-99 AE 1-1996, f. 1-23-96, cert. ef. 2-1-96 AE 1-1981, f. & ef. 3-5-81 AE 1-1979, f. 5-31-79, ef. 6-1-79 AE 2-1978, f. & ef. 3-6-78 AE 6, f. 6-5-69 AE 5, f. 12-22-64
This rule cites
- OAR 806-010-0050 — resolved
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/