OAR 340-210-0225: Notice of Construction and Approval of Plans: Types of Construction/Modification Changes

Edition: Current OARD snapshotEffective: 2023-03-01Last verified: 2026-09-07

Official history and status

Statutory/Other Authority: ORS 468.020, 468A.025, 468A.040, 468A.050, ORS 468A.055, 468A.070 & 468A.310

Statutes/Other Implemented: ORS 468A.025, 468A.035, 468A.040, 468A.050, 468A.055, 468A.070 & 468A.310

History: DEQ 19-2022, amend filed 11/18/2022, effective 03/01/2023 DEQ 7-2015, f. & cert. ef. 4-16-15 DEQ 6-2001, f. 6-18-01, cert. ef. 7-1-01, Renumbered from 340-210-0220 DEQ 14-1999, f. & cert. ef. 10-14-99, Renumbered from 340-028-0820 DEQ 19-1993, f. & cert. ef. 11-4-93 DEQ 12-1993, f. & cert. ef. 9-24-93, Renumbered from 340-020-0030 DEQ 4-1993, f. & cert. ef. 3-10-93 DEQ 5-1989, f. 4-24-89, cert. ef. 5-1-89 DEQ 15, f. 6-12-70, ef. 9-1-70

This rule cites

Cited by

Official source: https://secure.sos.state.or.us/oard/