(1) Every person claiming a lien created under ORS 87.010 (1) or (2) shall perfect the lien not later than 75 days after the person has ceased to provide labor, rent equipment or furnish materials or 75 days after completion of construction, whichever is earlier. Every other person claiming a lien created under ORS 87.010 shall perfect the lien not later than 75 days after the completion of construction. All liens claimed shall be perfected as provided by subsections (2) to (4) of this section. (2) A lien created under ORS 87.010 shall be perfected by filing a claim of lien with the recording officer of the county or counties in which the improvement, or some part thereof, is situated. (3) A claim of lien shall contain: (a) A true statement of demand, after deducting all just credits and offsets; (b) The name of the owner, or reputed owner, if known; (c) The name of the person by whom the claimant was employed or to whom the claimant furnished the materials or rented the equipment or by whom contributions are owed; and (d) A description of the property to be charged with the lien sufficient for identification, including the address if known. (4) The claim of lien shall be verified by the oath of the person filing or of some other person having knowledge of the facts, subject to the criminal penalties for false swearing provided under ORS 162.075. [Amended by 1961 c.609 §1; 1973 c.671 §3; 1975 c.466 §10; 1983 c.517 §1; 1985 c.596 §1; 1987 c.662 §6]
This rule cites
- ORS 87.010 — resolved
- ORS 162.075 — resolved
Cited by
- ORS 87.007: Protection from construction liens perfected after sale of residential property completed; requirements; seller options; rules; delivery of form to purchaser; penalty; damages; defenses.
- ORS 87.021: Notice to owners; notice from owner to original contractor; effect of failure to give notice.
- ORS 87.025: Priority of perfected liens; right to sell improvements separately from land; notice to mortgagee; list of materials or supplies.
- ORS 87.036: Subcontractor’s perfection of claim of lien; notice; fee; rules.
- ORS 87.039: Notice of filing claim of lien; effect of failure to give notice.
- ORS 87.045: Completion date of improvement; notice of completion, abandonment or nonabandonment; contents of notice.
- ORS 87.055: Duration of lien; when suit to enforce lien commences.
- ORS 87.060: Foreclosure; right to jury trial; distribution of proceeds of foreclosure sale.
- ORS 87.070: Amount of recovery by contractor; respective rights of contractor and owner.
- ORS 87.076: Bond or deposit of money; amount; demand for release of lien; effect.
- ORS 94.856: Assessment of common expenses as lien; recording; foreclosure; fees; remedies; exception.
- ORS 545.275: Lien on crops for water supplied for irrigation; enforcement; attorney fees.
- OAR 808-004-0530: Construction Lien Claims
- OAR 812-012-0140: Requirements for Notice of Compliance with Homebuyer Protection Act
- OAR 812-012-0145: Surety Bond Issued to Protect Purchasers of Residential Property from Lien Claims
- OAR 812-012-0150: Letter of Credit Issued to Protect Purchasers of Residential Property from Lien Claims
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors087.html