ORS 758.440: Order of commission on application.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) On the basis of the application, or, if there is a hearing, on the record made at the hearing held pursuant to ORS 758.435, the Public Utility Commission shall enter an order either approving or disapproving the application as filed, or as amended, together with findings of the facts supporting such order. (2) The commission, before approving an application for the allocation of territory, shall find that the applicant is exclusively serving the territory covered by the application and in the case of an adjacent unserved area that it is more economical and feasible to serve by an extension of the applicant’s existing facilities than by an extension of the facilities of another person. [Formerly 757.645; 1985 c.633 §2]
Administrative rules citing this section
- OAR 860-025-0010: Applications for Approval of Contracts to Avoid or Eliminate Duplicate Utility Service for Electric Utilities, Gas Utilities, and Large Telecommunications Utilities — implements
- OAR 860-025-0015: Applications for Approval of Amendments to Contracts to Avoid or Eliminate Duplicate Utility Service — implements
- OAR 860-025-0020: Applications for Allocation of Exclusively Served Territory for Electric Utilities, Gas Utilities, and Large Telecommunications Utilities — implements
- OAR 860-025-0025: Applications for Allocation of Exclusively Served Territory and Adjacent Unserved Territory for Electric Utilities, Gas Utilities, and Large Telecommunications Utilities — implements
- OAR 860-025-0027: Application to Transfer Rights to Allocated Territory for Electric Utilities, Gas Utilities, and Large Telecommunications Utilities — implements
This rule cites
- ORS 758.435 — resolved
Cited by
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors758.html