ORS 757.622: Commission to establish terms and conditions for default electricity service to nonresidential consumers.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
The Public Utility Commission shall establish the terms and conditions for providing default electricity service for nonresidential electricity consumers in an emergency. The commission also shall establish reasonable terms and conditions for providing default service to a nonresidential electricity consumer in circumstances when the consumer is receiving electricity services through direct access and elects instead to receive such services through the default service. The terms and conditions for default service established by the commission shall provide for viable competition among electricity service suppliers. [1999 c.865 §4a]
Administrative rules citing this section
- OAR 330-140-0010: Scope and Applicability of These Rules — implements
- OAR 330-140-0010: Scope and Applicability of These Rules — authority
- OAR 330-140-0020: Definitions as Used in This Division — implements
- OAR 330-140-0020: Definitions as Used in This Division — authority
- OAR 330-140-0030: Eligibility as a Self-Directing Consumer — implements
- OAR 330-140-0030: Eligibility as a Self-Directing Consumer — authority
- OAR 330-140-0040: Pre-certification of New Cost-effective Energy Efficiency Projects — implements
- OAR 330-140-0040: Pre-certification of New Cost-effective Energy Efficiency Projects — authority
- OAR 330-140-0050: Pre-certification of New Renewable Resource Purchase — implements
- OAR 330-140-0050: Pre-certification of New Renewable Resource Purchase — authority
- OAR 330-140-0055: Pre-certification of Investments in Distribution System-Connected Technologies — implements
- OAR 330-140-0055: Pre-certification of Investments in Distribution System-Connected Technologies — authority
- OAR 330-140-0060: Certification of Qualifying Expenditure for New Cost-effective Energy Efficiency Projects — implements
- OAR 330-140-0060: Certification of Qualifying Expenditure for New Cost-effective Energy Efficiency Projects — authority
- OAR 330-140-0070: Certification of Qualifying Expenditure for New Renewable Resources — implements
- OAR 330-140-0070: Certification of Qualifying Expenditure for New Renewable Resources — authority
- OAR 330-140-0075: Certification of Qualifying Expenditure for Investment in Distribution System-Connected Technologies — implements
- OAR 330-140-0075: Certification of Qualifying Expenditure for Investment in Distribution System-Connected Technologies — authority
- OAR 330-140-0080: Claiming a Credit Against Public Purpose Charges or Amount Charged in Rates Pursuant to ORS 757.054(4) — implements
- OAR 330-140-0080: Claiming a Credit Against Public Purpose Charges or Amount Charged in Rates Pursuant to ORS 757.054(4) — authority
- OAR 330-140-0120: Denial or Revocation of Eligibility to Participate as a Self-Directing Consumer — implements
- OAR 330-140-0120: Denial or Revocation of Eligibility to Participate as a Self-Directing Consumer — authority
- OAR 330-140-0140: Administrative Cost Recovery — implements
- OAR 330-140-0140: Administrative Cost Recovery — authority
- OAR 860-038-0005: Definitions for Direct Access Regulation — implements
- OAR 860-038-0170: Non-bypassable Charges — implements
- OAR 860-038-0290: Preferential Curtailment — implements
- OAR 860-038-0300: Electric Company and Electricity Service Suppliers Labeling Requirements — implements
- OAR 860-038-0405: ESS Emissions Planning Report — implements
- OAR 860-038-0590: Transmission and Distribution Access — implements
- OAR 860-038-0740: New Large Load Program Enrollment and Rates — implements
This rule cites
No citations extracted.
Cited by
No inbound citations found.
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors757.html