ORS 479.550: No work on new electrical installation until permit issued; temporary permit; rules.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) Except as provided in ORS 479.540, no person shall work on any new electrical installation for which a permit has not been issued. (2) The Electrical and Elevator Board shall adopt by rule provisions to require a city or a county to issue a temporary permit to be used for emergency or unanticipated work which will be valid for seven days to a licensed electrical contractor prior to the start of an electrical installation to allow contractor response prior to purchase of the actual electrical permit. (3) The board shall require a city or a county to revoke the temporary permit of the licensed electrical contractor who fails to comply with the Electrical Safety Law. [1959 c.406 §5; 1981 c.815 §9; subsections (2) and (3) enacted as 1991 c.368 §2; 1993 c.744 §120]
Administrative rules citing this section
- OAR 918-309-0080: Temporary Electrical Permit Rule — implements
This rule cites
- ORS 479.540 — resolved
Cited by
- ORS 455.156: Municipal investigation and enforcement of certain violations; notice of civil penalty; department to develop programs; defense for violation of building inspection program.
- ORS 479.540: Exemptions; rules.
- OAR 918-261-0000: Partial Board Exemption for Medical Diagnostic Imaging and Therapy Equipment
- OAR 918-309-0080: Temporary Electrical Permit Rule
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors479.html