ORS 366.292: Consideration of tolling prior to doing modernization project.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
ORS sections in this chapter were amended or repealed by the Legislative Assembly during its 2025 special session. See the table of ORS sections amended or repealed during the 2025 special session: 2025 ss A&R Tables New sections of law were enacted by the Legislative Assembly during its 2025 special session and pertain to or are likely to be compiled in this ORS
Before proceeding with a modernization project, or a series of modernization projects on a single highway, that might result in a segment of highway to which tolling could reasonably be applied, the Department of Transportation shall determine what portion of the costs of construction and maintenance could be recovered through tolls on users of the project. The toll potential of a modernization project shall be considered among other factors in determining which modernization projects should be included in the Statewide Transportation Improvement Program, with those projects with the greater potential to be self-funded through tolls ranking higher. A determination under this section may be based on assumptions that a single toll would be imposed or on assumptions that tolls would be imposed that vary depending on time of day or any other condition the department deems relevant. [1999 c.1072 §2]
This rule cites
No citations extracted.
Cited by
No inbound citations found.
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors366.html