ORS 276.910: Use of fuel cell power systems in state agency facilities; rules.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) Before constructing or renovating a major facility, an authorized state agency shall, after comparing various equipment options and to the greatest extent practicable, use fuel cell power systems for emergency backup power applications and for critical power applications in lieu of other equipment options. (2)(a) The State Department of Energy shall, in consultation with the Oregon Department of Administrative Services, adopt rules establishing criteria for the comparison of fuel cell power systems and other equipment options required by subsection (1) of this section. (b) Criteria to be established under this subsection must address: (A) The impact of emissions, including but not limited to nitrous oxide, sulfur oxide, carbon monoxide, carbon dioxide and particulates, from various equipment options, on the environment, regardless of whether the equipment is installed indoors or installed outdoors; (B) Life cycle costs, including but not limited to acquisition costs, installation and commissioning costs, siting and permitting costs, maintenance costs and fueling and decommissioning costs; and (C) The complexity of equipment options and any ancillary equipment. [2009 c.748 §6]
Official history and status
History: Note: 276.910 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 276 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.
Administrative rules citing this section
- OAR 330-130-0010: Purpose — authority
- OAR 330-130-0020: Definitions — authority
- OAR 330-130-0030: Notification — authority
- OAR 330-130-0040: Procedures for Class 1 Buildings — authority
- OAR 330-130-0050: Procedures for Class 2 Buildings — authority
- OAR 330-130-0055: Procedure for Leased Buildings — implements
- OAR 330-130-0060: Service Charges — authority
- OAR 330-130-0070: Department Administrative Procedures — authority
- OAR 330-130-0080: Procedures for Monitoring the Reduction in Energy Use by State Agencies — authority
- OAR 330-130-0090: Pre-qualification for persons performing Energy Analysis and Energy Savings Performance Contracting Services — implements
- OAR 330-130-0100: Pre-qualification for persons performing Energy Commissioning, Auditing, and Performance Verification Services — implements
- OAR 330-130-0500: Use of Fuel Cell Power Systems — implements
- OAR 330-130-0500: Use of Fuel Cell Power Systems — authority
This rule cites
No citations extracted.
Cited by
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors276.html