ORS 197.633: Two phases of periodic review; rules; appeal of decision on work program; schedule for completion; extension of time on appeal.
Edition: 2025 EditionEffective: 2026-01-01Last verified: 2026-09-07
(1) The periodic review process is divided into two phases. Phase one is the evaluation of the existing comprehensive plan, land use regulations and citizen involvement program and, if necessary, the development of a work program to make needed changes to the comprehensive plan or land use regulations. Phase two is the completion of work tasks outlined in the work program. (2) The Land Conservation and Development Commission shall adopt rules for conducting periodic review that address: (a) Initiating periodic review; (b) Citizen participation; (c) The participation of state agencies; (d) The preparation, review and approval of a work program; and (e) The preparation, review and approval of work tasks, including: (A) The amendment of an urban growth boundary. (B) The designation of, or withdrawal of territory from, urban reserves or rural reserves. (3) The rules adopted by the commission under this section may include, but are not limited to, provisions concerning standing, requirements to raise issues before local government as a precondition to commission review and other provisions concerning the scope and standard for commission review to simplify or speed the review. The commission shall confine its review of evidence to the local record. The commission’s standard of review: (a) For evidentiary issues, is whether there is substantial evidence in the record as a whole to support the local government’s decision. (b) For procedural issues, is whether the local government failed to follow the procedures applicable to the matter before the local government in a manner that prejudiced the substantial rights of a party to the proceeding. (c) For issues concerning compliance with applicable laws, is whether the local government’s decision on the whole complies with applicable statutes, statewide land use planning goals, administrative rules, the comprehensive plan, the regional framework plan, the functional plan and land use regulations. The commission shall defer to a local government’s interpretation of the comprehensive plan or land use regulations in the manner provided in ORS 197.829. For purposes of this paragraph, “complies” has the meaning given the term “compliance” in the phrase “compliance with the goals” in ORS 197.627. (4) A decision by the Director of the Department of Land Conservation and Development to approve a work program, that no work program is necessary or that no further work is necessary is final and not subject to appeal. (5) The director: (a) Shall take action on a work task not later than 120 days after the local government submits the work task for review unless the local government waives the 120-day deadline or the commission grants the director an extension. If the director does not take action within the time period required by this subsection, the work task is deemed approved. The department shall provide a letter to the local government certifying that the work task is approved unless an interested party has filed a timely objection to the work task consistent with administrative rules for conducting periodic review. (b) May approve or remand a work task or refer the work task to the commission for a decision. A decision by the director to approve or remand a work task may be appealed to the commission. (6) Except as provided in this subsection, the commission shall take action on the appeal or referral of a work task within 90 days of the appeal or referral. Action by the commission in response to an appeal from a decision of the director or a referral is a final order subject to judicial review in the manner provided in ORS 197.650 and 197.651. The commission may extend the time for taking action on the appeal or referral if the commission finds that: (a) The appeal or referral is appropriate for mediation; (b) The appeal or referral raises new or complex issues of fact or law that make it unreasonable for the commission to give adequate consideration to the issues within the 90-day limit; or (c) The parties to the appeal and the commission agree to an extension, not to exceed an additional 90 days. (7) The commission and a local government shall attempt to complete periodic review within three years after approval of a work program. To promote the timely completion of periodic review, the commission shall establish a system of incentives to encourage local government compliance with timelines in periodic review work programs. [1991 c.612 §3; 1993 c.18 §38; 1999 c.622 §3; 2001 c.527 §1; 2005 c.829 §4; 2011 c.469 §2]
Administrative rules citing this section
- OAR 660-012-0060: Plan and Land Use Regulation Amendments — implements
- OAR 660-018-0060: Who May Appeal — implements
- OAR 660-024-0010: Definitions — implements
- OAR 660-024-0040: Land Need — implements
- OAR 660-024-0050: Land Inventory and Response to Deficiency — implements
- OAR 660-024-0060: Metro Boundary Location Alternatives Analysis — implements
- OAR 660-024-0065: Establishment of Study Area to Evaluate Land for Inclusion in the UGB — implements
- OAR 660-024-0067: Evaluation of Land in the Study Area for Inclusion in the UGB; Priorities — implements
- OAR 660-024-0070: UGB Adjustments — implements
- OAR 660-025-0030: Periodic Review Schedule — implements
- OAR 660-025-0035: Initiating Periodic Review Outside the Schedule — implements
- OAR 660-025-0040: Exclusive Jurisdiction of LCDC — implements
- OAR 660-025-0040: Exclusive Jurisdiction of LCDC — authority
- OAR 660-025-0050: Commencing Periodic Review — implements
- OAR 660-025-0060: Periodic Review Assistance Team(s) — implements
- OAR 660-025-0070: Need for Periodic Review — implements
- OAR 660-025-0080: Notice and Citizen Involvement — implements
- OAR 660-025-0085: Commission Hearings Notice and Procedures — implements
- OAR 660-025-0090: Evaluation, Work Program or Decision that No Work Is Necessary — implements
- OAR 660-025-0100: Notice and Filing of Objections (Work Program Phase) — implements
- OAR 660-025-0110: Director and Commission Action (Work Program Phase) — implements
- OAR 660-025-0130: Submission of Completed Work Task — implements
- OAR 660-025-0130: Submission of Completed Work Task — authority
- OAR 660-025-0140: Notice and Filing of Objections (Work Task Phase) — implements
- OAR 660-025-0150: Director Action and Appeal of Director Action (Work Task Phase) — implements
- OAR 660-025-0160: Commission Review of Referrals and Appeals (Work Task Phase) — implements
- OAR 660-025-0160: Commission Review of Referrals and Appeals (Work Task Phase) — authority
- OAR 660-025-0170: Modification of an Approved Work Program, Extensions, and Sanctions for Failure to Meet Deadlines — implements
- OAR 660-025-0175: Review of UGB Amendments and Urban Reserve Area Designations — implements
- OAR 660-025-0180: Stay Provisions — implements
- OAR 660-025-0185: Review of Urban Growth Boundary Amendment Components — authority
- OAR 660-025-0230: Applicability — implements
- OAR 660-037-0010: Purpose Statement — implements
- OAR 660-037-0020: Policy — implements
- OAR 660-037-0030: Statement of Applicability — implements
- OAR 660-037-0040: Definitions — implements
- OAR 660-037-0050: Minimum Water-Dependent Shoreland Protection Acreage — implements
- OAR 660-037-0060: Designate Water-Dependent Shorelands — implements
- OAR 660-037-0070: Water-Dependent Shoreland Locational and Suitability Criteria — implements
- OAR 660-037-0080: Methods of Protection — implements
- OAR 660-037-0090: Rezoning of Qualifying Shorelands to Nonwater-Dependent Uses — implements
This rule cites
- ORS 197.829 — resolved
- ORS 197.627 — resolved
- ORS 197.650 — resolved
- 197.651 — resolved
Cited by
- ORS 197.180: State agency planning responsibilities; determination of compliance with goals and compatibility with plans; coordination between agencies and local governments; rules; exceptions.
- ORS 197.626: Submission of land use decisions that expand urban growth boundary or designate urban or rural reserves.
- ORS 215.503: Legislative act by ordinance; mailed notice to individual property owners required by county for land use actions.
- ORS 227.186: Notice to property owners of hearing on certain zone change; form of notice; exceptions; reimbursement of cost.
- OAR 660-004-0035: Appeal of an Exception
- OAR 660-023-0250: Applicability
- OAR 660-025-0040: Exclusive Jurisdiction of LCDC
- OAR 660-025-0085: Commission Hearings Notice and Procedures
- OAR 660-025-0160: Commission Review of Referrals and Appeals (Work Task Phase)
- OAR 660-025-0175: Review of UGB Amendments and Urban Reserve Area Designations
- OAR 660-025-0210: Updated Planning Documents
- OAR 660-032-0000: Purpose and Applicability
Official source: https://www.oregonlegislature.gov/bills_laws/ors/ors197.html