OAR 952-001-0080: Operators to Respond to Notifications Requesting Design Information
Edition: Current OARD snapshotEffective: 2019-01-01Last verified: 2026-09-07
(1) Within 10 business days after a designer notifies the Oregon Utility Notification Center of a proposed project, the operator of the underground facilities must: (a) Mark within 24 inches of the outside lateral dimensions of both sides of all its locatable underground facilities within the area of proposed excavation. All marks must indicate the name, initials or logo of the operator of the underground facilities, and the width of the facility if it is greater than 2 inches; (b) Provide the excavator the best description available to the operator of the unlocatable underground facilities in the area of the proposed excavation including as-constructed drawings, or other facility maps that are maintained by the facility operator; or (c) Contact the person requesting design information and agree on a time, prior to the beginning of the proposed project, for exchange of the information required under subsection (a) or subsection (b) of this section of this rule. (2) If a designer intends to perform work at multiple sites or over a large area, the designer must take reasonable steps to work with the facility operators, including preconstruction meetings, so that the operators may locate their facilities at a time reasonably in advance of the actual start of survey or design for each phase of work.
Official history and status
Statutory/Other Authority: ORS 757.552
Statutes/Other Implemented: ORS 757.552
History: OUNC 1-2018, amend filed 12/26/2018, effective 01/01/2019 OUNC 1-2014, f. & cert. ef. 3-7-14 OUNC 1-1997, f. & cert. ef. 4-17-97
This rule cites
- this rule — target_record_not_published
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/