OAR 952-001-0040: Pre-Marking Required by the Excavator; Exemption
Edition: Current OARD snapshotEffective: 2014-03-07Last verified: 2026-09-07
(1) Except as provided in section (2) of this rule, prior to notifying the Oregon Utility Notification Center, an excavator must pre-mark with the color white the immediate area of the proposed excavation within both the public rights-of-way and underground easements. (2) An excavator need not pre-mark as required in section (1) of this rule if: (a) The operator can determine precisely the direction, length and location of the proposed excavation by referring to a locate ticket; or (b) Before the beginning of the proposed project, the excavator and the operator met at the construction site to exchange the information required under section (1) of this rule.
Official history and status
Statutory/Other Authority: ORS 757.552
Statutes/Other Implemented: ORS 757.552
History: OUNC 1-2014, f. & cert. ef. 3-7-14 OUNC 1-1997, f. & cert. ef. 4-17-97
This rule cites
- section (2) of this rule — target_record_not_published
- section (1) of this rule — target_record_not_published
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/