OAR 918-271-0010: Calls for Inspection
Edition: Current OARD snapshotEffective: 2000-10-01Last verified: 2026-09-07
(1) All persons who take out an electrical permit, homeowners as well as electrical contractors, shall request an inspection within three working days of: (a) The completion of any electrical installation intended to be covered or concealed or that is intended to be placed into service before the final electrical inspection; and (b) The completion of all electrical installations for the job site covered by a particular permit. (2) Transactions under a master inspection permit are covered by separate requirements.
Official history and status
Statutory/Other Authority: ORS 479.730
Statutes/Other Implemented: ORS 479.730
History: BCD 23-2000, f. 9-29-00, cert. ef. 10-1-00 BCD 19-1996, f. 9-17-96, cert. ef. 10-1-96