OAR 860-084-0210: Capacity Reservation, Timing, and Duration
Edition: Current OARD snapshotEffective: 2011-09-30Last verified: 2026-09-07
(1) A capacity reservation expires if a completed interconnection application is not filed within two months of the reservation start date or if the system has not been installed within twelve months of the reservation start date, unless a waiver is granted under OAR 860-084-0000. Any delay resulting from the utility not completing required work to connect the eligible system to the grid will be excluded from this 12-month installation requirement. (2) Once the capacity reservation expires, the retail electricity consumer must newly apply for a capacity reservation and will not be given preferential treatment.
Official history and status
Statutory/Other Authority: ORS 757.360 - 757.380
Statutes/Other Implemented: ORS 757.360 - 757.380
History: PUC 7-2011, f. & cert. ef. 9-30-11 PUC 2-2010, f. & cert. ef. 6-1-10
This rule cites
- OAR 860-084-0000 — resolved
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/