OAR 860-038-0760: Reporting
Edition: Current OARD snapshotEffective: 2018-09-18Last verified: 2026-09-07
Each electric company must file a status report to the Commission within two months of total enrollment in New Large Load Direct Access Programs reaching 25 average megawatts, 50 average megawatts, 100 average megawatts, and 80 percent of any enrollment limit adopted by the Commission.
Official history and status
Statutory/Other Authority: ORS Ch. 183, 756, 757
Statutes/Other Implemented: ORS 756.040, 757.600 through 757.667
History: PUC 6-2018, adopt filed 09/18/2018, effective 09/18/2018
This rule cites
No citations extracted.
Cited by
Official source: https://secure.sos.state.or.us/oard/