OAR 860-029-0047: Integration Charges
Edition: Current OARD snapshotEffective: 2023-07-26Last verified: 2026-09-07
(1) Each public utility may assess Commission-approved integration charges on wind and solar qualifying facilities that are located within the public utility's Balancing Authority Area. (2) The public utility bears the burden to establish the proposed integration charge or charges reflecting the costs of integrating the type of resource that will be subject to the charges. (3) To the extent they are to be imposed by the public utility, any integration charges must be included in the public utility's avoided cost schedules.