OAR 736-149-0830: Temporary rule language in effect until 10/19/2026. Contractor Progress Payments
Edition: Current OARD snapshotEffective: 2026-04-24Last verified: 2026-09-07
(1) Request for progress payments. Each month the contractor shall submit to the department its written request for a progress payment based upon an estimated percentage of contract completion. At the department's discretion, this request may also include the value of material to be incorporated in the completed work that has been delivered to the premises and appropriately stored. The sum of these estimates is referred to as the "value of completed work." With these estimates as a base, the department will make a progress payment to the contractor, which shall be equal to: (a) The value of completed work; (b) Less those amounts that have been previously paid; (c) Less other amounts that may be deductible or owing and due to the department for any cause; and (d) Less the appropriate amount of retainage. (2) Progress payments do not mean acceptance of work. Progress payments shall not be construed as an acceptance or approval of any part of the work, and shall not relieve the contractor of responsibility for defective workmanship or material.
Official history and status
Statutory/Other Authority: ORS 279.025(3)(k)
Statutes/Other Implemented: ORS 279.025(3)(k)
History: PRD 2-2026, temporary adopt filed 04/23/2026, effective 04/24/2026 through 10/19/2026
This rule cites
No citations extracted.
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/