OAR 734-010-0460: Final Inspection
Edition: Current OARD snapshotEffective: 2022-01-13Last verified: 2026-09-07
(1) Notification of Completion; inspection. The Contractor shall notify ODOT in Writing when the Contractor considers the on-site Contract Work completed. Within 15 Days of receiving the Contractor's notice, ODOT will inspect the project and project records, and will either accept the Work or notify the Contractor of remaining Work to be performed. (2) Acknowledgment of acceptance. When ODOT finds that all Work required under the Contract, both on-site and administrative, has been completed satisfactorily, ODOT shall acknowledge acceptance of the Work in Writing.
Official history and status
Statutory/Other Authority: ORS 184.616, 184.619, 279A.065 & 279A.050
Statutes/Other Implemented: ORS 279C.570
History: DOT 1-2022, renumbered from 731-007-0320, filed 01/13/2022, effective 01/13/2022 DOT 2-2005, f. 2-16-05, cert. ef. 3-1-05
This rule cites
No citations extracted.
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/