OAR 731-148-0250: Solicitation Cancellation, Delay or Suspension; Rejection of All Proposals or Responses; Consultant Responsibility for Costs
Edition: Current OARD snapshotEffective: 2019-02-21Last verified: 2026-09-07
ODOT may cancel, delay or suspend a solicitation, RFQ or other preliminary Procurement document, whether related to OAR 731-148-0200 (Direct Appointment Procedure), OAR 731-148-0205 (Small Purchase Procedure), OAR 731-148-0210 (Informal Selection Procedure), OAR 731-148-0215 (Request for Qualifications) or OAR 731-148-0220 (Formal Selection Procedure), or reject all Proposals, responses to RFQs, responses to other preliminary Procurement documents, or any combination of the foregoing, if ODOT believes it is in the public interest to do so. In the event of any such cancellation, delay, suspension or rejection, ODOT is not liable to any Proposer for any loss or expense caused by or resulting from any such cancellation, delay, suspension or rejection. Consultants responding to either solicitations, RFQs or other preliminary Procurement documents are responsible for all costs they may incur in connection with submitting Proposals, responses to RFQs or responses to other preliminary Procurement documents.
Official history and status
Statutory/Other Authority: ORS 184.619, 279A.065(6)(a) & 279A.070
Statutes/Other Implemented: ORS 279A.050(3), 279A.065 & 279C.110
History: DOT 1-2019, adopt filed 02/21/2019, effective 02/21/2019
This rule cites
- OAR 731-148-0200 — resolved
- OAR 731-148-0205 — resolved
- OAR 731-148-0210 — target_record_not_published
- OAR 731-148-0215 — resolved
- OAR 731-148-0220 — resolved
Cited by
Official source: https://secure.sos.state.or.us/oard/