OAR 629-610-0080: Revegetation When Reforestation is Not Required
Edition: Current OARD snapshotEffective: 1995-01-01Last verified: 2026-09-07
When reforestation is not required or planned, the landowner shall ensure sufficient revegetation of the site to provide continuing soil productivity and stabilization within 12 months of the completion of the operation. Revegetation required by this rule may be planted or naturally established, and shall consist of trees, shrubs, grasses, or forbs suitable for soil stabilization and productivity protection. Landowners are encouraged to revegetate the operation area with native plants.
Official history and status
Statutory/Other Authority: ORS 527.710
Statutes/Other Implemented: ORS 527.745
History: FB 5-1994, F. 12-23-94, cert. ef. 1-1-95
This rule cites
- this rule — target_record_not_published
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/