OAR 345-027-0350: Changes Requiring an Amendment
Edition: Current OARD snapshotEffective: 2020-01-28Last verified: 2026-09-07
Except for changes allowed under OAR 345-027-0353, an amendment to a site certificate is required to: (1) Transfer ownership of the facility or the certificate holder as described in OAR 345-027-0400; (2) Apply later-adopted laws as described in OAR 345-027-0390; (3) Extend the construction beginning or completion deadline as described in OAR 345-027-0385; (4) Design, construct, or operate a facility in a manner different from the description in the site certificate, if the proposed change: (a) Could result in a significant adverse impact that the Council has not addressed in an earlier order and the impact affects a resource or interest protected by an applicable law or Council standard; (b) Could impair the certificate holder’s ability to comply with a site certificate condition; or (c) Could require a new condition or a change to a condition in the site certificate.
Official history and status
Statutory/Other Authority: ORS 469.470
Statutes/Other Implemented: ORS 469.405
History: EFSC 1-2020, adopt filed 01/28/2020, effective 01/28/2020 EFSC 9-2019, temporary adopt filed 08/22/2019, effective 08/22/2019 through 02/17/2020
This rule cites
- OAR 345-027-0353 — resolved
- OAR 345-027-0400 — resolved
- OAR 345-027-0390 — resolved
- OAR 345-027-0385 — resolved
Cited by
- OAR 345-027-0240: Conditions
- OAR 345-027-0351: Review Processes for Requests for Amendment
- OAR 345-027-0355: Written Evaluations for Changes Not Requiring Amendment
- OAR 345-027-0357: Amendment Determination Request
- OAR 345-027-0360: Preliminary Request for Amendment
- OAR 345-027-0365: Proposed Order for a Request for Amendment
- OAR 345-029-0020: Notice of Violation
Official source: https://secure.sos.state.or.us/oard/