OAR 340-239-0300: Construction Activities
Edition: Current OARD snapshotEffective: 2021-10-04Last verified: 2026-09-07
The requirements of OAR 340-239-0200 do not apply to the working face of the landfill or to areas of the landfill surface where the landfill cover material has been removed and solid waste has been exposed for the purpose of installing, expanding, replacing, or repairing components of the landfill gas, leachate, or gas condensate collection and removal system, for conducting a remedial action, or for law enforcement activities requiring excavation; as long as these areas are kept to the minimum size and time duration as possible.
Official history and status
Statutory/Other Authority: ORS 468.020, ORS 468A.025, ORS 468A.040 & ORS 468A.050
Statutes/Other Implemented: ORS 468A.025, ORS 468A.040 & ORS 468A.050
History: DEQ 16-2021, adopt filed 10/04/2021, effective 10/04/2021