OAR 340-141-0282: Plan Maintenance and Use
Edition: Current OARD snapshotEffective: 2021-05-20Last verified: 2026-09-07
(1) At least one copy of the plan must be kept in a central location accessible at any time by the incident commander or spill response manager named in accordance with OAR 340-141-0265(7). (2) A High Hazard Rail owner or their designee must implement the plan in the event of a spill. The owner of the High Hazard Rail Line must receive approval from DEQ before it conducts any major aspect of the spill response contrary to the plan unless: (a) Such actions are necessary to protect human health and safety; (b) Such actions must be performed immediately in response to unforeseen conditions to avoid additional environmental damage; or (c) The plan holder has been directed to perform such actions by the Department or the United States Coast Guard.
Official history and status
Statutory/Other Authority: ORS 468B.437
Statutes/Other Implemented: ORS 468B.300 - 468B.500
History: DEQ 8-2021, adopt filed 05/20/2021, effective 05/20/2021
This rule cites
- OAR 340-141-0265 — resolved
Cited by
Official source: https://secure.sos.state.or.us/oard/