OAR 340-141-0210: Plan Maintenance and Use
Edition: Current OARD snapshotEffective: 2021-05-20Last verified: 2026-09-07
(1) At least one copy of the plan must be kept in a central location accessible at any time by the incident commander or spill response manager named in accordance with OAR 340-141-0140(7). Each facility covered by the plan must possess a copy of the plan and keep it in a conspicuous and accessible location. (2) A field document prepared under OAR 340-141-0130(5) must be available to all appropriate personnel. Each covered vessel covered by the plan must possess a copy of the field document and keep it in a conspicuous and accessible location. (3) A facility, covered vessel, owner or operator or their designee must implement the plan in the event of a spill. The owner or operator of the facility or covered vessel must receive approval from DEQ before it conducts any major aspect of the spill response contrary to the plan unless: (a) Such actions are necessary to protect human health and safety; (b) Such actions must be performed immediately in response to unforeseen conditions to avoid additional environmental damage; or (c) The plan holder has been directed to perform such actions by DEQ, EPA, Pipeline Hazardous Materials Safety Administration (PHMSA) or the United States Coast Guard.
Official history and status
Statutory/Other Authority: ORS 468.020 & 468B.345 - 468B.390
Statutes/Other Implemented: ORS 468B.345 - 468B.390
History: DEQ 8-2021, amend filed 05/20/2021, effective 05/20/2021 DEQ 2-2003, f. & cert. ef. 1-31-03
This rule cites
- OAR 340-141-0140 — resolved
- OAR 340-141-0130 — resolved
Cited by
Official source: https://secure.sos.state.or.us/oard/