OAR 340-052-0025: Approval of Plans
Edition: Current OARD snapshotEffective: 1981-02-06Last verified: 2026-09-07
(1) Approval of plans shall be in writing. (2) Final review of plans will commence upon receipt of all appropriate and required submittal data and shall be completed within a reasonable period of time commensurate with the nature and complexity of the project. (3) Approval may be provisional. (4) Approval of plans may be deferred pending satisfaction of other requirements including but not limited to: (a) Issuance of either a WPCF or a NPDES permit; (b) Obtaining a surety bond or substitute as may be required by ORS 454.425.
Official history and status
Statutory/Other Authority: ORS 468
Statutes/Other Implemented: ORS 468B.055
History: DEQ 3-1981, f. & ef. 2-6-81
This rule cites
- ORS 454.425 — target_record_not_published