OAR 340-045-0050: Denial of an NPDES or WPCF Permit
Edition: Current OARD snapshotEffective: 2017-11-01Last verified: 2026-09-07
DEQ will promptly notify the applicant in writing of the denial of a permit application under OAR 340-011-0097. The notification will include the reasons for denial. The denial will become effective 20 days from the date of service of the notice unless within that time DEQ receives a request for a hearing. The applicant must make the request for a hearing in writing and state the grounds for the request. DEQ will conduct the hearing as a contested case hearing under ORS 183.413 through 183.470 and OAR chapter 340, division 011.
Official history and status
Statutory/Other Authority: ORS 468
Statutes/Other Implemented: ORS 468.065 & 468.070
History: DEQ 15-2017, amend filed 10/31/2017, effective 11/01/2017 DEQ 15-2000, f. & cert. ef. 10-11-00 DEQ 113, f. & ef. 5-10-76 DEQ 58, f. 9-21-73, ef. 10-25-73 DEQ 53(Temp), f. & ef. 6-21-73 thru 10-18-73
This rule cites
- OAR 340-011-0097 — target_record_not_published
- ORS 183.413 — resolved
- 183.470 — resolved
Cited by
Official source: https://secure.sos.state.or.us/oard/