OAR 330-025-0030: Rejection of Deficient Submission
Edition: Current OARD snapshotEffective: 1982-03-12Last verified: 2026-09-07
If the resource plan submitted by an electric Utility fails to satisfy requirements of OAR 330-025-0020, the Director shall reject the submission and require the Utility to submit a new plan which remedies the deficiencies. The Director may specify the date by which the resubmission shall be made.
Official history and status
Statutory/Other Authority: ORS 469
Statutes/Other Implemented: ORS 469.080
History: DOE 4-1982, f. & ef. 3-12-82
This rule cites
- OAR 330-025-0020 — resolved
Cited by
No inbound citations found.