OAR 141-120-0220: Jurisdictions Not Governed by this Rule
Edition: Current OARD snapshotEffective: 1994-10-20Last verified: 2026-09-07
A jurisdiction that submits a WCP to the Division within six months from the date this rule is adopted may be exempt from the requirements of OAR 141-120-0000 to 141-120-0230 if, within 90 days from adoption of this rule, the jurisdiction demonstrates to the Director’s satisfaction that the jurisdiction has made substantial progress toward designating wetland resources for protection, conservation or development and analysing alternatives to adversely impacting wetlands by other means.
Official history and status
Statutory/Other Authority: ORS 196.692
Statutes/Other Implemented: ORS 196.678 - 196.692, 215 & 227.350
History: LB 6-1994, f. & cert. ef. 10-20-94
This rule cites
- this rule — target_record_not_published
- OAR 141-120-0000 — resolved
- 141-120-0230 — resolved
Cited by
No inbound citations found.
Official source: https://secure.sos.state.or.us/oard/