OAR 137-049-0490: Foreign Contractor
Edition: Current OARD snapshotEffective: 2005-03-01Last verified: 2026-09-07
If the Contract Price exceeds $10,000 and the Contractor is a Foreign Contractor, the Contractor shall promptly report to the Oregon Department of Revenue on forms provided by the Department of Revenue, the Contract Price, terms of payment, Contract duration and such other information as the Department of Revenue may require before final payment can be made on the Contract. A copy of the report shall be forwarded to the Contracting Agency. The Contracting Agency Awarding the Contract shall satisfy itself that the above requirements have been complied with before it issues final payment on the Contract.
Official history and status
Statutory/Other Authority: ORS 279A.065
Statutes/Other Implemented: ORS 279A.120
History: DOJ 11-2004, f. 9-1-04, cert. ef. 3-1-05